Browse Forums Building A New House Re: Custom in Hills District - Windows Installed! 45Oct 05, 2013 9:08 pm 18/03/15 Deposit 02/09/15 CDC 22/09/15 Slab 05/12/15 Frames 15/12/15 Brick started. 11/04/16 Roof start 04/05/16 Roof finish 09/07/16 Gyprock. Re: Custom in Hills District - Scrape to Brickwork in 1 mont 60Oct 29, 2013 8:51 pm Fascia ( Surfmist ) and gutter ( monument ) installed today. Piers were rendered on Saturday. Build thread: here Land Nov 12, Contract 6/07/13, Consent 15/08/13, Start 20/09/13, Slab 25/09/13, Frame 4/10/13, Brick 21/10/13, Roof 2/11/13, Lock-up 17/12/13, Handover 3/3/14 Ideally you would engage a landscaper to give you some insight what they may need in the space to make your vision come to life… 1 14572 Yes, I was happy with the work, bar a few small things. Overall, communication could have been better though. However, I found them reliable and did good work at a… 4 63413 Thanks again Simeon for being so elaborate. Appreciate it. Its gives us a very idea. Kind Regards 4 4335 |