Browse Forums Building A New House Re: Custom Build in Hills District - Major Progress! 23Sep 06, 2013 10:26 pm 18/03/15 Deposit 02/09/15 CDC 22/09/15 Slab 05/12/15 Frames 15/12/15 Brick started. 11/04/16 Roof start 04/05/16 Roof finish 09/07/16 Gyprock. Re: Custom in Hills District - Slab! 39Sep 29, 2013 10:31 pm 18/03/15 Deposit 02/09/15 CDC 22/09/15 Slab 05/12/15 Frames 15/12/15 Brick started. 11/04/16 Roof start 04/05/16 Roof finish 09/07/16 Gyprock. Re: Custom in Hills District - Slab! 40Sep 30, 2013 5:55 pm Drainage and electrical earthworks today. Gravel installed to prevent erosion / mud. Drainage and electrical earthworks. More stormwater connections. Rear yard evened off, more fill installed, sewage inspection port (S10). Hopefully I won't be paying for the fill. Build thread: here Land Nov 12, Contract 6/07/13, Consent 15/08/13, Start 20/09/13, Slab 25/09/13, Frame 4/10/13, Brick 21/10/13, Roof 2/11/13, Lock-up 17/12/13, Handover 3/3/14 Ideally you would engage a landscaper to give you some insight what they may need in the space to make your vision come to life… 1 14216 Yes, I was happy with the work, bar a few small things. Overall, communication could have been better though. However, I found them reliable and did good work at a… 4 61167 Thanks again Simeon for being so elaborate. Appreciate it. Its gives us a very idea. Kind Regards 4 4125 |