Well I think I have stalked for long enough now & it's about time I started my own thread!
So this is going to be our second home in Australia however our first build so we know roughly what we want however not sure on how it all works
We chose Redink because we took our list of what we want & how we want it to a few builders & Redink came back with a pretty good design that only needed tweaking slightly (still not heard back from all of them )
We have purchased a 900sqm block in Lakeland's so we have plenty of room to play with so wanted a reasonably sized house on there with room for a pool and a nice size garden.
So here is our design would love to hear everyone's feed back so feel free to put forward your thoughts & ideas & I will start my list ready for pre start.
There are a few changes we have already decided on but won't be doing these until pre start now.
We have our Interior Design Consultation next week & hopefully pre start won't be far behind.
Like ⋅ Add a comment ⋅ Pin to Ideaboard ⋅
Timeline
Signed up 7/7/13
Interior Design 9/9/13
Contracts 11/9/13
Prestart 17/10/13
Building permit 10/12/13
Tap13/12/13
Site works 27/01/14
Slab 17/02/14
Brick work started 12/03/14
Brick work finished 3/4/14
Roof frame complete 15/4/14
Colorbond 21/4/14
White set finished 8/05/14
LOCKED UP 20/05/14
Cabinets 29/05/14