Started with 4 then went between 2 and 3. We are in the country so I think that makes a difference, on our last build in Perth tradies would work intermitantly at the house it was so frustrating. Kazzbah
Browse Forums Building A New House Re: Kazzbah's Redink build 26Jun 07, 2013 8:09 pm Building again . . with Redink Pre-start 04/12 Keys - 03/13 Finishing off. . . Painting/Floor Tiles/Carpet - 04/13 Walk In Robe/Lighting/Blinds and Moving 05/13 Gates/Front Landscaping / Pool 05/13 Re: Kazzbah's Redink build 27Jun 11, 2013 6:41 am Building in Myalup with Redink PCQ : Nov 2012 Prestart: 17 th March 2013 Builders Permit: Sept 2013 Completed build Aug 2014 viewtopic.php?f=31&t=67559 Re: Kazzbah's Redink build 28Jun 11, 2013 10:33 am Looks good Kazzbah. I love the front render colours. Our RedInk Build Thread - viewtopic.php?f=31&t=64118&p=1004131#p1004131 ** Timeline Page 1 Moved In - 19.12.13 Re: Kazzbah's Redink build 29Jun 23, 2013 7:12 pm Thanks everyone for your thoughts and compliments on our home, nothing has happened at all the short tiles have arrived on site but not tilers at this stage but staying postive that things will progress from this week, have had meeting with ss and as soon as tiling completed everything else will hopefully flow along at a good pace. Kazzbah Re: Kazzbah's Redink build 30Jun 23, 2013 9:04 pm Hi kazz. Nice plan and nice insides. Could you provide a timeline of important steps. Prestart siteworks slab etc. They certainly are dragging their feet aren't they. We were told that there is only an issue with bricklayers. This makes me nervous now. Re: Kazzbah's Redink build 31Jun 23, 2013 10:02 pm I'm thinking the same thing rex, we have been hit with the dreaded bricklayer shortage, site should be ready for brickies end of this week, beginning on next, but our CLO mentioned the shortage so I guess that means it ain't going to happen!!! I don't want to worry about other delays too! building with Redink Prestart 21/3/13 Slab down 12/6/13 Brickwork started 5/8/13 Brickwork finished 26/8/13 Roof frame 6/9/13 Colorbond 26/9/13 Grey float 11/10/13 white set 17/10/13 Re: Kazzbah's Redink build 32Jun 23, 2013 10:04 pm No don't worry rex777 we are building in the country not Perth and by the sound of Munchy's build you should be okay. I did my prestart in Sept last year slab was poured around the 30th Nov and bricking commenced around 8th Jan have just got bogged down by a few issues but hopefully all will start to come good this week onwards. Re: Kazzbah's Redink build 33Jun 25, 2013 2:10 pm it's looking great! love the big alfresco at the back Re: Kazzbah's Redink build 34Aug 09, 2013 7:57 pm Hey Kazzbah, how is the house coming along???? Our RedInk Build Thread - viewtopic.php?f=31&t=64118&p=1004131#p1004131 ** Timeline Page 1 Moved In - 19.12.13 Re: Kazzbah's Redink build 36Sep 15, 2013 10:31 am Hi Leanne, we haven't moved in but we had handover on Thursday, have cleaned the walls and are putting sealer on today. The work begins will post some pictures soon, Redink here present the homes really great at the end stage very impressed. Kazzbah Re: Kazzbah's Redink build 37Sep 15, 2013 10:48 am Cant wait to see some photos goodluck with it all painting the house is a big job (I remember clearly from current house) Re: Kazzbah's Redink build 38Sep 15, 2013 7:46 pm Gee kazzbah that is a long time between slab and handover. Can I ask why it has taken so long? Is it a country thing? You should have moved in in June not September. Re: Kazzbah's Redink build 39Sep 15, 2013 8:07 pm Hey rex777, yes it is a long time we were not happy one little bit about the build time, but what can you do you have signed a contract they never actually give you a completion date and the contract allows it to be dragged out to there build time based on worst case scenario about 282 working days, so there you have it. We are quite happy with our home much better than the previous we think at this stage so all good so far. Yes other builders up here complete there homes far quicker but in saying that we have got a hell of a lot of house for our $$$$. Kazzbah Re: Kazzbah's Redink build 40Sep 15, 2013 8:16 pm LeanneR Cant wait to see some photos goodluck with it all painting the house is a big job (I remember clearly from current house) Yes it sure is a big job did not want to go down the painting road again but can't justify the money to have it painted so have to suck it up, we are doing the fencing ourselves as well, went to Perth twice to purchase fencing and then went down on Friday and came back last night with a lounge suite and outdoor setting weather was horrendous for the whole trip. But pretty much all our shopping is done for now just finishing our part before the tiler comes in and then carpet and then we can move in properly . Cheers Kazzbah Thank you so much everyone. This all makes a lot of sense. I guess when you talk to a builder who butters up everything to look very polished, you get to start believing… 7 18951 Hi We have finally decided to complete a KDR on our corner plot in NE Melbourne suburbs. Given its a corner plot approx. 400 sqm just a standard design may not fit the… 0 9034 |