good news, the bank has coughed up the debit interest and refunded the entire application fee charged. a small victory for me, esp when taken in context against the interest that will be charged on the entire loan...
Browse Forums Home Finance Re: When do we receive our First Home Owners Grant? 44Apr 30, 2010 4:41 pm VICTORY 1800, EN-SUITE, DOUBLE GARAGE, FAMILY ROOM AND ALFRESCO Land Settled: 20 July 2010 Site Scrap: 30 August 2010 Slab Pour: 20 September 2010 Frame Complete: 23 September 2010 Fascia and Gutters: 28 September 2010 Roof Complete: 06 October 2010 Lock-up complete: 28 October 2010 Plaster complete: 29 October 2010 Fix-out complete: 22 Nov 2010 PCI 7 FEBRUARY 2011 Re: When do we receive our First Home Owners Grant? 49May 30, 2010 2:56 am We're building The Albany 330E with Casa Design & Construction via National Builders Group See how we are going here: https://forum.homeone.com.au/viewtopic.php?f=31&t=32694 Re: When do we receive our First Home Owners Grant? 51May 31, 2010 2:47 pm Metricon Riva 33 - http://herlihy-riva.blogspot.com Site start 15/03/2010 - Handover 23/12/2010 9 months and 8 days (284 calendar days) from site start to handover Re: When do we receive our First Home Owners Grant? 52May 31, 2010 3:05 pm We're building The Albany 330E with Casa Design & Construction via National Builders Group See how we are going here: https://forum.homeone.com.au/viewtopic.php?f=31&t=32694 Re: When do we receive our First Home Owners Grant? 53Jun 08, 2010 5:08 pm VICTORY 1800, EN-SUITE, DOUBLE GARAGE, FAMILY ROOM AND ALFRESCO Land Settled: 20 July 2010 Site Scrap: 30 August 2010 Slab Pour: 20 September 2010 Frame Complete: 23 September 2010 Fascia and Gutters: 28 September 2010 Roof Complete: 06 October 2010 Lock-up complete: 28 October 2010 Plaster complete: 29 October 2010 Fix-out complete: 22 Nov 2010 PCI 7 FEBRUARY 2011 Re: When do we receive our First Home Owners Grant? 54Jun 30, 2010 5:54 pm VICTORY 1800, EN-SUITE, DOUBLE GARAGE, FAMILY ROOM AND ALFRESCO Land Settled: 20 July 2010 Site Scrap: 30 August 2010 Slab Pour: 20 September 2010 Frame Complete: 23 September 2010 Fascia and Gutters: 28 September 2010 Roof Complete: 06 October 2010 Lock-up complete: 28 October 2010 Plaster complete: 29 October 2010 Fix-out complete: 22 Nov 2010 PCI 7 FEBRUARY 2011 Re: When do we receive our First Home Owners Grant? 55Jul 05, 2010 9:27 am Pepto, we did not need the FHOG at settlement, we used the money we had declared as our deposit to the bank as our deposit. If the FHOG is part of your deposit then things may be different. In any case you should be bugging your broker/bank/conveyancer to give you precise figures on how much you are expected to contribute. Then make sure you have a few thousand extra in case they revise the figure. At our settlement, the bank forgot to authorize their settlement agent to actually settle! And the settlement agent decided to tell us this on the day of settlement!! Luckily our solicitor was on the ball and bullied the bank into settling on time. Metricon Riva 33 - http://herlihy-riva.blogspot.com Site start 15/03/2010 - Handover 23/12/2010 9 months and 8 days (284 calendar days) from site start to handover So it looks like we finally have some movement on site! Definitely later than expected, but I'll take any progress at this point. I'll drop by over the weekend to get… 5 27693 We already paid for somfy motors for the blinds. The quote above was purely for “pre-wiring” so the blinds company can install the motors and blinds. That’s why we… 5 16268 11 41615 |