been searching through BCA, AS3959, and lots of internet searching, interested to see what people have done where a new renovation that has to be done to BAL-FZ (Flame Zone) is joining onto a 1970's project home?
The original house has a lot of wood cladding, window frame etc... almost all framing is oregon and windows are cedar, but it will have a Flame zone spec roof fascias and eves.
(Picture is not my house - but similar enough to show the issues where the windows meet the roof and there is a large gap that the builders say they wil just bridge with Fibre Cement)
The builder says they can just butt joint the flame zone eve (eg 15mm plywood, 16mm fyrechek plaster, 4.5mm fibre cement) up against a 50yr old piece of western red cedar and it's ok - doesn't make sense.
This can't be a new problem, what did the building consent conditions and the building certifiers say about this?
Was it just passed or did they make the new renovation section continue on until it joined with a more compliance material eg Brick, etc..
My main issues is the windows - the window frame run floor through to the roof without a break.
Interested to hear peoples experiences.
Thanks