You will need to establish an overall design,budget, work out the materials, quants and apply realistic rates for the trade components.
Don't be too fussy at the preliminary stage 1, as you fill in the details and firm up quotes try to stay within the defined boundaries, Generally it should take several iterations ie
1. 2D Sketch-> rough quants
2. Construction/Engineering 3D Drawings/Details->accurate quants
2- Storey, Masonry, Timber Frame, Truss Beam Slab Details
3. Trade Estimate/Quote & check feedback into 2 above
Getting the Best Info, Data and use from a site/project

Goodluck
Related
28/09/2023
8
Carlisle KDR site cost after second soil test

Building A New House

We were lucky in that our old house was so small (86 square metres) compared to the new house, they were able to take enough readings around the old backyard house before…

20/08/2023
21
Builder suspended works, demanding variations, cost increase

Building A New House

Fair Trading can issue orders to rectify and complete but once the matter goes to NCAT these orders are automatically vacated. You will have to terminate contract and sue…

You are here
Building ForumOwner Builder Forum
Home
Pros
Forum