Browse Forums Owner Builder Forum Re: What parts of the build did the budget blowout during OB 5Oct 14, 2011 3:01 pm kayandandy This is where we blew out * bathroom fixtures and fittings * cabinetry * tiling This was because I chose rectified tiles and had them done floor to ceiling in five bathrooms! I had everything that could open and close in our kitchen. Our bathrooms were very simple but smple costs cash ..... oh and the wooden bath! Rubbish removal ..... this costs loads Thanks. I know what you mean with bathrooms. In all my reno's, I found the easiest place to blow a budget is the bathroom...and you had 5 of them!! I think I only factored in 2k for rubbish removal(not including original cut fill and footings). Do you think that's enough. The more I think of it, the more I'd imagine it's not. I need to replace some lengths of aluminum shower frame but I can't seem to find any suppliers of this stuff. Neither the blue or orange home centers carry these things.… 0 5398 Coming back to your old stomping grounds, huh? Renovations on a budget can be quite the journey. It's like giving your house a new lease on life. The twist of not knowing… 1 3476 Can you give advice on how to get missing certificates needed for a form 21? Our bank requires us to provide one but we are missing 4 building certificates from our first… 3 71810 |