I am currently building a new workshop (9.5m x 4m) and have already poured the strip footing according to council regulations however I have hit a hurdle.
The plan is to build a standard stud wall on top of a lower (800mm high) concrete block wall and secure the stud wall via threaded starter bars (reinforcing rods) through the base plate and concrete blocks and epoxy them into the concrete.
The challenge is that I had planned to use Adbri 90mm split face concrete blocks (100 series) however the 90mm blocks have only approx. 30mm holes, and they do not line up when stacked on top of each other, making it near impossible to locate the threaded rods in the concrete.
Does anyone have any ideas on the best way to locate the threaded rods and or secure the structure to the concrete?
Cheers Froudie