Order of Progress in Building a new house on a slab.
Sort of.......some things may get changed around.
Just a rough idea of the order of progress you would normally expect.
Site Survey.
Site scrape for concrete slab.
Plumbing waste.
Elec rough in for meter.
Slab.
Elec Meter connected.
Site clean to level out for other trades.
Frame.
............sometimes the brickies also comes at frame stage to build the garage.
Roof trusses.
Windows/door jambs installed.
Fascia and Gutter.
Roof.
Plumbing rough in.
Sisalation wrap........interchangeable with Plumbing rough in.
Bricklayer.
Lock up Carpenter.
Elec rough in, and also Comms rough in.
Wall fluff Insulation.
Plaster.
Kitchen.
Final fix. (carpenter)
Tiler.
Paint.
Not exhaustive, but a start