Hi guys
anyone have any experience with cut and fill in a sloping site 11° with S type soil. Only really wanted to know whether anyone has use some of the cut to fill the lower slope. Any advice would be appreciated.
Browse Forums Owner Builder Forum Re: Cut and fill help 2Oct 16, 2019 8:33 am Designer,Engineer (Civil,Const & Envir),Builder,Concrete & Masonry Contract.Struct Repairs Re: Cut and fill help 4Oct 17, 2019 9:03 am Hi divo247 Thanks for the info You shouldn't have any issues At s guess there's approx. 70m3 of concrete? I suggest you break down the build/trade components further and get 3 estimates as it's a big slab. hth Designer,Engineer (Civil,Const & Envir),Builder,Concrete & Masonry Contract.Struct Repairs 2 6227 Versaloc is a mortarless besser block system that still needs a properly engineered footing. If you just do a 400x200 footing it will fail in time. At 17m long you need it… 1 21837 PM me your email. I have a build excavation calculator you can use based on your plans to double check what your builder is telling you. Cheers Simeon 1 10595 |