I am new to this forum, so plz excuse me if you find some of my questions dumb/stupid.
I am about to sign my building contract with one of the Volume builders in Victoria. They have sent me a modified version of HIA contract. Here are some areas where I need some guidance from the experts on this forum;
1: I have an FSC agreed already. But they want me to sign a clause which covers them for extra cost in case some contamination is discovered on site. My question is, aren't they responsible for investigating the same during Foundations data collection ( Via soil testing) prior to signing a contract with me.
2: They have recommended a building Surveyor from their side in the contract and want me to sign him as if I had appointed him. is there any difference between the Site surveyor and a site inspector( that I was hoping to appoint for stage wise inspections).
Also if a building surveyor is needed, who pays for it? Builder or owner.
How much cost are we talking abt here in case I have to pay for him.
3: They want me to sign the final stage and make the final payment but without installing the appliances. They are saying that they will install the appliances later when I have settled in to prevent theft and damage. Is this a regular practice as I find this strange.
4: Is it normal for builders to ignore Method 1 and force the owners into signing on Method 2.
5: What sort of delay penalties are a normal practice. They are suggesting 250/week which is much lower than my actual cost. What is a recommended and achievable number?
6: Is it normal in today's time that the builder is requesting for 300+ days to build a house.
7: Who is responsible for Planning approval. They want me to do this.
8: How much time is reasonable nowadays to get a bank to approve finances after you sign the contract.
Too many questions