Week 24 Update - visited the site today and house seems very much is final shape. So from completion point of view, Tiles and electrical work completed. Bath tub installed and now waiting for the shower screen installation.
Cleaners are booked in for this week. Once site cleaned, the sanding of first floor to be started to prepare for the carpeting and so does for timber on ground floor. Final coat of paint to be done next week.
Still quite small but essential work is due like sealant application which will be performed sometime next week. 1st week of December is expected to commence driveway work.
As per current estimation final walk through to be scheduled in 3rd week of January 2021 followed by handover before 1st week of Feb 2021.
Thanks