Hi All,
I was hoping the great community here can shed some light. I've been trying to get some indications from my vendor but no luck.
I've bought a townhouse OTP which was under construction in Mount Waverley. The corner land is about 650m2 with two townhouse. About 22-24sq each, double storey, 4-3-2. The land is split almost down the middle.
The current stage is almost at Lock up (only the main door and garage door is missing).
The following is done for both townhouses:
- internal and ceiling plaster boards
- Levelling of plaster boards and cut outs for electrical points
- Door frames and architraves
- Floorboards (not sanded or polished yet)
- Kitchen cabinets (only benchtop and tapwares missing)
- Cabinets in bathrooms and laundry
- Skirting and cornice
- Stairs
- External downpipes
The tiler is currently finishing up the wall tiles in the bathrooms.
Things left to do (I think):
- painting
- Install electrical points, lights etc.
- Install air-conditioning
- Kitchen, toilet and laundry benchtop
- Sand and polish floorboards
- Install tapwares, range hood, oven etc.
- Driveway and external landscaping
I was initially told that the completion date is end of October. Is it realistic? From the progress, I think it can be done but will be a push.
Anyone can give an idea how long is the council approval/registration process?
Appreciate any feedback.
Thanks.