After Stalking many Coral Home build threads, it's time to start my own. We have only just paid the initial $1,750 deposit & our land is subject to finance, so we have a long way to go!
Timeline: (To Be Updated)
Initial meet with Coral Homes: 8/9/19
Initial Deposit paid: 21/9/19
Official Contract signed: 19/10/19
Beaumont Tiles appointment: 16/11/19
National Tiles appointment: 23/11/19
Land Settlement: 18/12/19
Clipsal Appointment: 7/01/20
Building Approval: 19/02/20
Colours Appointment: 24/02/20
Final Plans Received: 27/03/20
Start Date: 8/04/20
Slab Poured: 20/04/20
Frame Complete: 1/05/20
Roof Complete: 8/05/20
Brick Complete: 29/05/2020
Render Complete: 5/06/20
Kitchen Stone & Garage Door Installed: 15/06/20
Tile Complete: 19/06/20
Painting Complete: 29/06/20
Fit-offs Complete: 3/06/20
Carpet Installation & Touch ups: 10/06/20