Interim Occupational Certificate change coming
Page 1 of 1
Apparently the change is coming on September 1, 2019 and it was delayed from 2018.
What is the real impact for owners who are nearing completion later this year?
Thy
https://www.claytonutz.com/knowledge/20 ... ember-2019
https://www.planning.nsw.gov.au/Policy- ... ubdivision
My understanding is that you can no longer get an interim certificate you can only get the full certificate, so things like driveways will need to be completed before you move in.
That’s the part I’m worried about.
It’s supposed to kick in on Sept 1.
But imagine if everyone on here has to now complete their full house including driveway etc before they move in....
My understanding is that you can no longer get an interim certificate you can only get the full certificate, so things like driveways will need to be completed before you move in.
That’s the part I’m worried about.
It’s supposed to kick in on Sept 1.
But imagine if everyone on here has to now complete their full house including driveway etc before they move in....
We’ve had the keys since mid May and we haven’t yet got the drive way sorted. So yes it will cause all sorts of issues if they don’t modify what is needed
Related
23/03/2024
2
Please read what the conditions are when receive final payment invoice.
9/10/2023
2
Hi Simeon, Thank you for laying it down for us. Makes sense. Appreciate it very much. Have a nice day. Cheers
25/05/2023
1
Get some long brass machine screws and bolt right through the gate and put brass acorn nuts and washers on the other side. It will never come off