Browse Forums Building A New House 1 Jun 25, 2019 3:24 pm I've been reading through the other Ausbuild topics but haven't seen any for Element yet! We're still in the really early stages but these are the dates we have so far: Prelim land contract signed: 25th May 2019 Land contract received: 5th June 2019 Prelim build contract signed: 7th June 2019 Land contract signed: 16th June 2019 Build contract signed: 6th July 2019 Tile selection: 16th July 2019 Colour selection: 16th July 2019 Electrical appointment: 22nd July 2019 We ended up having to delay our financing for some time but are now back on track. Land settlement: 6th December 2019 Slab Pour: 10th January We've gone with the Rosemont on Lot 49. Any tips/suggestions or things to be aware of is of course greatly appreciated too! I’m curious about how you went with this. We are planning a KDRB and considering Plantation Homes as a builder. I’m aware that after the demolition another soil test… 1 6317 i wouldn't be worried, you'll definitely miss something, no matter how many times you review. we've spent close to 5 months ensuring everything got reflected in the… 5 9437 Thanks for your reply. I will just wait and see I guess. Trying to get some more information from our builder. 9 11713 |