Hi, when a new house is built in an older area, such as knock down and rebuild or a sub divide, at what stage is the site reconnected to electricity, water, gas and nbn/phone? As well as my reno project, I'm building a pair of new houses as a sub division. My NBN hub is being down by the builder, but
- when will Telstra come out to connect them? Apparently they need 3-6 months notice, is that right?
- when will the houses get connected to electricity again? How long when when they are built does an electricity retailer normally take to come along and plug the house in? How much does a connection normally cost?
I know they could be questions to ask the builder but, once you sign the contract to build man, their response time becomes infuriating