Just about to start building our new home with Ausbuild at Harrington Estate in Bridgeman Downs.
Will post updates and progress photos here
Timeline so far:
21/5 Build contract signed
11/6 Land registered
25/7 Land settled
28/7 Build contract signed
13/7 Tile selections
24/7 Colour and electrical selection
4/9 File handed over to construction team
12/9 Slab
19/9 Frame
28/9 Roof, gutter and facia
5/10 Windows and front door installed
12/10 Wall sarking, gas, aircon, plumbing and electrical rough-in
9/11 Lock-up
26/11 Painting commenced