Hey Guys,
I've been on this site a while ago but lost my log on details so thought I'd start fresh.
In January we purchased our first block of land in Angle Vale, it's a nice 2000sqm patch of dirt in where we will be building our dream home.
We have chosen to build the two story Cleo through Simonds Homes.
Since buying our block in Angle Vale we have completed selections, all the approvals, contracts and we are currently in council approval. We have been told a max 4 weeks (been two weeks already) and we should be ready to order materials to our block
Excited to share our journey, ups & downs and pictures with you guys as well as read other people's forums.
Look forward to getting to know you all.
Land settlement 17/12/2013
Tile Appointment 15/02/2014
Selections 27/02/2014
Contract signing 02/04/2014
Council Approval 08/08/2014 (6weeks in council)
Site Scrape 10/09/2014
Footings complete 12/09/2014
Plumbing completed 15/09/2014
Slab 19/09/2014
Septic 26/09/2014
Site power & underground services 29/09/2014
Framework delivered 01/10/2014
Downstairs frame work completed 02/10/2014
Windows and doors delivered on site 08/10/2014
Top story frame work started 20/10/2014
Top story frame work completed 21/10/2014
Windows & doors installed 21/10/2014
Roof frame started 22/10/2014
Fascias & gutters on & roof tiles delivered 27/10/2014
roof tiles complete 28/10/2014
Bricks delivered 28/10/2014
Wrapped 30/10/2014
Air conditioning 03/11/2014
Plumbing 04/11/2014
Bricks started 05/11/2014
Insulation delivered 06/11/2014
Bricks completed 21/11/2014
Eaves completed 24/11/2014
Site clean 05/12/2014
Garage Roof frame 05/12/2014
Electrical 1st fix 09/12/2014
Insulation complete 09/12/2014
Downstairs walls completed 10/11/2014
Bricks cleaned 14/12/2014
Garage roof tiled 15/12/2014
Upstairs walls complete 18/12/2014
LOCKUP 19/12/2014
Doors installed 05/01/2015
Kitchen installed 13/01/2015
Front door on 15/01/2015
Stairs installed 15/01/2015
Water proofing 18/01/2015
Painting started 19/01/2015
Painting completed 23/01/2015
Staircase enclosed 27/01/2015
Tiles started 27/01/2015
Tiles completed 03/02/2015
Painting completed 03/02/2015
Kitchen completed 03/02/2015
Balcony balustrade installed 03/02/2015
Plumbing second fix complete 04/02/2015
Facade cladding started 09/02/2015
Kitchen sink installed 09/02/2015
Electrical second fix 12/02/2015
PCI appointment 19/02/2015
Site clean 22/02/2015
Tiles 22/02/2015
Carpet 23/02/2015
Appliances installed 24/02/2015
Handover 25/02/2015
Splash back 27/02/2015