Longreach 33- Our country home
Page 1 of 3
14/9/18 tile appointment
25/9/18 plans submitted to private certifier
11/10/18 clipspec appointment via skype
12/10/18 plans then sent to Cessnock council for old fashioned approval
25/19/18 colours appointment
29/10/18 plans approved by Cessnock council. Very fast indeed
6/11/18 VAC approved
Start date given to break ground 10th December
Our outside colours
Austral bricks- governors range Wakehurst with RAKED off white mortar
Roof/gutters and fascia- monument
Garage door- knotwood Redgum
Windows- surfmist
Front door and posts - walnut stain
Cement sheeting above back sliders/ tank- parchment
Internal colours
Bathroom /en-suite /laundry tiles- belga ivory(floors) 600x300, United white gloss subway 100x300 (all walls up to 2100)
Total upgrade cost $2597
Kitchen splash back- Devonshire white gloss subways 75x150
Carpet- laguna keys wild rice (bronze range) upgrading to 10mm premium underlay
Total upgrade cost $1550
Timber laminate- oak natural tradition classic 1050 range (standard)
Caesarstone- ice snow (included) waterfall edges $1200 upgrade
Kitchen door handles and bathroom handles- Matane (standard range!!!!)
Electrical appointment- via Skype
Have to admit this process was very confusing and left us baffled. With the colour and tile appointment we were able to prepare and choose our selections before the actual appointment however with the Clipsal appointment this was not available so decisions had to be done on the spot.
We ended up putting in provisions for down lights and other lighting so we could buy our own and the have electrician install for cash. In saying that , with extra power points etc etc etc we ended up spending $2218 extra. And still need to buy our pendants fans and Dow lights etc. Hoping beacon have a sale after Xmas for these items.
10th December 2018- on schedule. Pad is levelled.
End of week one 15th dec 2028, piers poured, plumbing in. Heaps of rain this week so site is a bit of a muddy mess
17th Dec 2018- more rain. đ©
19th Dec 2018- quarter minus going in for slab foundations. We were a little shocked that we werenât getting a waffle slab!
21st December 2018- concrete guys have half finished forming up for the slab. They go on 3 weeks break now so wonât have a slab till half way thru January. The site supervisor was hoping to pour today but due to the weather this isnât happening. All good though.
Looks great. What facade did you go with?
Looks great. What facade did you go with?
HI Forever Rosehill, we designed our own facade as we didnt really like any of the coral facades. We have a portico that comes out about 1.8 metres and 2.1 metres wide. We are having 2 x 140mm stained timber posts which will match the front door. Once we have handover ,we are building a deck out to the eaves. Are you building in Rosehill estate too?
Looks great. What facade did you go with?
HI Forever Rosehill, we designed our own facade as we didnt really like any of the coral facades. We have a portico that comes out about 1.8 metres and 2.1 metres wide. We are having 2 x 140mm stained timber posts which will match the front door. Once we have handover ,we are building a deck out to the eaves. Are you building in Rosehill estate too?
Yep Rosehill Estate We are lot 309.
We have changed our facade as well trying to make it a bit different. We went with a Hamptons look portico.
[quote="Country Home"]
Looks great. What facade did you go with?
HI Forever Rosehill, we designed our own facade as we didnt really like any of the coral facades. We have a portico that comes out about 1.8 metres and 2.1 metres wide. We are having 2 x 140mm stained timber posts which will match the front door. Once we have handover ,we are building a deck out to the eaves. Are you building in Rosehill estate too?
Yep Rosehill Estate We are lot 309.
We have changed our facade as well trying to make it a bit different. We went with a Hamptons look portico.
[/quote]your plans look really good I like the changes. I have sent you a pm with our pics
Friday 18th January 2019. Tradies back Christmas leave and finished form work. Slab poured in 44 degree heat. Crazy.
Saturday 19th January 2019
Began erecting steel frame. Most walls completed. Trusses next.
Related
3/03/2024
5
We already paid for somfy motors for the blinds. The quote above was purely for âpre-wiringâ so the blinds company can install the motors and blinds. Thatâs why we…
8/11/2023
1
of course there are legal avenues. You've already mentioned it. Sue them. I find it odd that lawyers wouldnt be willing to take on the case, given CCT evidence and…
22/01/2024
36
"Losers" "humanity" "off time" "your" "top notch" "love symbol" Sounds like ponzo is done using other people's toilets