Coral Homes Noosa 23 - South Ripley
Page 1 of 5
We are building in the Providence estate in South Ripley, Queensland.
So far our timeline has been:
Contract for land sign: 20/01/18 (Expected registration September 2018)
Preliminary Agreement signed and Paid with Coral Homes: 14/04/18
Contract Signing with Coral Homes: 1/6/18
Tile Appointment: 14/6/18
Colour Appointment: 20/6/18
Electrical Appointment: 22/6/18
Land Registered: 21/12/18
Plans submitted to council: 14/01/18
Land Settlement: 29/01/19
Plumbing Approval: 22/02/19 (28 business days)
Building Approval: 22/02/19 (28 business days)
Start Date: 1/04/19
PCI: 2/7/19
Handover: 11/7/19
Week 1:
* Site scrape
* Piers and footings poured
* Plumbing installed
* Toilet Delivered
Week 2:
* Formwork Installed
* Waffle pods installed
* Slab poured
* Frame walls installed
Week 3:
* Roof Frame installed
Week 4 (Easter week):
* Gutters and Fascia installed
* Safety Railing installed
Week 5:
* Roof installed
* Insulation wrapped
* Front door delivered
* Windows and external doors delivered.
* Front door Installed
* Windows and external doors installed.
Week 6:
* Plasterboard installed
* Bricks started
* Walls patches
Week 7:
* Cornices installed
* Bricks continue
* Waterproofing done
* Bricks continued
Week 8
* Tiles started and finished (except splash backs)
* Cabinetry installed
* Bathroom sinks installed
* Door frames installed
* Doors installed
* Bricks continued
Week 9
* Skirting installed
* Door frames/architraves finished
* Pantry shelving installed
* Pantry sliding door installed
* Eaves installed
* FC above windows installed
* Front rendered
* Downpipes installed
* External door handles installed (locked out)
* Caeserstone installed
Week 10
* Internal painting completed
* Eaves painted
* Front door stained
Week 11
* Wardrobe doors installed
* Plumbing fixtures installed: Taps, Showers, bath, toilet, laundry tub
* Mirrors installed
* Shower screens installed
* Garage door installed
* Render painted
* FC above windows painted
* Downpipes painted
* Electrical fitout completed
UPGRADES:
Bathroom
* Timber look doors to vanity in main bathroom: $57
* Freestanding Bath: $295
* Ceiling mounted showerhead: $37
* 450x650 shower niche x 2: $986
TOTAL: $1375
Kitchen
* Caeserstone & overhead cupboard promotion: $999
* 900mm freestanding gas stove: $999
* Waterfall edges: $1156
* Tiles behind rangehood: $110
* Tiles laid in herringbone: $41
* Dishwasher: $882
TOTAL: $4187
Laundry
* Splashback tiles laid in brickbond: $3
Miscellaneous
* Flooring: Free promotion
* Upgrade to vinyl: $89
* 2550mm ceilings promotion: $1999
* 1200mm front door: $499
* Steel frame: Free promotion
* Colorbond Roof: Free promotion
TOTAL: $2587
External
* Render to front: $1487
* Off white mortar: $377
* Flyscreens to all openings except front door: $2400
TOTAL: $4264
Electrical
* Lights (batten): $990
* 3 button switch: $6.20
* 2 way lights: $54
* Cooker switch: $97
* Single power points: $252.50
* Double power points: $1248
* Outdoor power point: $105
* Power point to island bench: $80
* Aircon wiring: $331
* Tv points: $164
* Fans: $1326.92
* Fan switch mechanisms: $239
* Exhaust fans: $751
* Smoke alarms: $1032
* Install supplied exterior lights: $172
TOTAL: $6,848.62
- $3830 (standard inclusions)
Extra Spent: $3018.62
Below is our current floor plan and Land Disclosure Plan
Changes include:
- Deleting giant hole in wall between Dining & Lounge
- Deleting the Study Nook located behind the pantry and extending the pantry into this space.
[img:11mahvj9]https://forum.homeone.com.au/u/1_1542693142.JPG[/img:11mahvj9]
[img:11mahvj9]https://forum.homeone.com.au/u/1_1542693272.JPG[/img:11mahvj9]
We r building with coral next year
So we will watch ur post for inspiration
Cheers
Hello Amy! its rhani!
Oh hey! I'm following your build on here as well
Congrats! Following your build. We will be starting next year as well
Awesome! I'm following yours too, can't wait to see it start!
Following, we are building in haigslea and our land settles a couple of days after you guys
Can't wait to follow your build too!
Following this build as well. Just paid soil testing deposit on 7/01/19 and waiting to hearback. Hopefully this week. Also going with a Noosa 23 MkII with some modifications.
Hi Josh,
That's very exciting! We are having our soil test done on Thursday. Where are you building?
Following this build as well. Just paid soil testing deposit on 7/01/19 and waiting to hearback. Hopefully this week. Also going with a Noosa 23 MkII with some modifications.
Hi Josh,
That's very exciting! We are having our soil test done on Thursday. Where are you building?
We are building on Brisbane Northside.
Keen to follow your build process.
We have just signed up with Coral to build our 1st home.
Cheers
Hi,
Keen to follow your build process.
We have just signed up with Coral to build our 1st home.
Cheers
Keen to follow your build process.
We have just signed up with Coral to build our 1st home.
Cheers
Welcome,
What design are you going with and where are you building?
A modified Milan 25, at Harvest Rise estate.
Hi,
Keen to follow your build process.
We have just signed up with Coral to build our 1st home.
Cheers
Keen to follow your build process.
We have just signed up with Coral to build our 1st home.
Cheers
Hi!
I can't wait to follow your build either!
Soil results came back as a H1 last week which is what we were quoted for so we are definitely happy with the result. Made a few modifications to the build and inclusions. Sent it off late last week. Will follow up today to make sure they received all the information and will try get an ETA for draft plans + contract. How long was it approx for you from deposit to contract? We were told roughly ~2 weeks.
Hi Josh,
That's awesome that you got a good result! We are still waiting for our results but we chose fixed site costs so it won't effect us.
We waited 4 weeks between deposit and contract signing but I think it was a very busy time of year then as it was right before EOFY.
Soil results came back as a H1 last week which is what we were quoted for so we are definitely happy with the result. Made a few modifications to the build and inclusions. Sent it off late last week. Will follow up today to make sure they received all the information and will try get an ETA for draft plans + contract. How long was it approx for you from deposit to contract? We were told roughly ~2 weeks.
Hi Josh,
That's awesome that you got a good result! We are still waiting for our results but we chose fixed site costs so it won't effect us.
We waited 4 weeks between deposit and contract signing but I think it was a very busy time of year then as it was right before EOFY.
Thanks for that Amy.
FYI We paid deposit 7/1
Results came back 21/01 (2 week turnaround as expected)
Hopefully won't be too long before we get the contract
Related
2/11/2023
2
Ask the council if there is a chance of getting build over easement exemption. Sometimes easements are unused and 24cm is not all that much. Good luck. And yes any builder…
14/04/2024
1
In Qld it is a requirement that a builder must have a cost breakdown, for building a home to the same specification, with the same inclusions and the same finish. So ask…
9/08/2023
4
Well these guys are not looking good... I sent them a written enquiry last week and they have not yet replied. If they cannot respond to a simple…