Browse Forums Building A New House 1 Nov 04, 2018 3:59 pm 08/17 Sales were very helpful in the design of our home Washington 32 with the Sante Fe facade. 11/17 Contract signed and deposit paid. file the to Admin 04/18 Finally a DA approval after 5 months delays due to Admin Staff turnover and file left in limbo for about 2 months . 07/18 Finally concrete slab finally done 10/18 Frames brickwork and roofing done thanks to a very favourable winter weatherwise no rain delays. 10/18 internal fitout now delayed due to a dispute re quote with tile supplier Di Lorenzo . Matter has been referred to NSW Fair trading department for intervention. We spent close to 2 years in a process with TA. It was horrible..... we got to tender, and the first cut was 50% over our budget which "they care such about meeting ". We… 18 27275 go upvc window frames ensure insulation under colorbond. not just sarking, lighter color roof also not sure if you have seen this viewtopic.php?t=5823 last couple of pages… 4 110566 |