Browse Forums Building A New House Re: Building with CJ Homes 15Jun 15, 2019 1:40 pm 14/6/2019: Fixing inspection takes place with a new inspector as well as a new supervisor. I learn that the previous supervisor has been reassigned to maintenance works. There are 3 tradies (painters) on site at the time of inspection. The work presents generally well. A few minor defects (chips, brick discolouration, dirt) are identified. A lot of work is incomplete and cannot be inspected. Despite being invoiced for fixing stage, the following are missing/incomplete at the time of inspection: - electrical work - toilets, showers, completion of sink installation, sealants - door handles for all internal doors - some paint of the cladding - stormwater system Because of all the dirt and protection for the paint job, a number of items cannot be inspected. The estimated practical completion date is the 13/07 (~150 days after the start date). I am looking forward to the progress in the next couple of weeks. The driveway and landscaping should start in 2 weeks time. As shown below, cladding painting job is in progress. We can clearly see discolouration in the brickwork. However, we'll have to wait until after the bricks have been cleaned. Like ⋅ Add a comment ⋅ Pin to Ideaboard ⋅ Re: Building with CJ Homes 16May 24, 2020 2:16 am onlyann 14/6/2019: Fixing inspection takes place with a new inspector as well as a new supervisor. I learn that the previous supervisor has been reassigned to maintenance works. There are 3 tradies (painters) on site at the time of inspection. The work presents generally well. A few minor defects (chips, brick discolouration, dirt) are identified. A lot of work is incomplete and cannot be inspected. Despite being invoiced for fixing stage, the following are missing/incomplete at the time of inspection: - electrical work - toilets, showers, completion of sink installation, sealants - door handles for all internal doors - some paint of the cladding - stormwater system Because of all the dirt and protection for the paint job, a number of items cannot be inspected. The estimated practical completion date is the 13/07 (~150 days after the start date). I am looking forward to the progress in the next couple of weeks. The driveway and landscaping should start in 2 weeks time. As shown below, cladding painting job is in progress. We can clearly see discolouration in the brickwork. However, we'll have to wait until after the bricks have been cleaned. Like ⋅ Add a comment ⋅ Pin to Ideaboard ⋅ Thank you so much for the step by step information, it's really very helpful. Re: Building with CJ Homes 18Feb 22, 2022 9:03 pm Hello, Lovely home. Can you share some of the upgrades you made and pricing? Thanks! Ask for references and speak to them. If they are defensive or try to avoid the request, walk. 1 74709 I would never build with Fowler homes. I built with them in 2021 and till date maintenance issues are pending. All their existing trades and businesses don't work with… 14 105567 Hi there! Putting the feelers out there for those who have (or almost) built with Arli homes! Interested in your experiences who've built from their stock home designs… 0 23492 |