Yesterday we had the electric hot water system removed (sold on gumtree! $$) and solar hot water installed. The concrete company was also there to do all the excavation, as well as formwork for the back and side paths. There probably were some other things, but my brain was mush by the end of the day.
The back and side paths were concreted today and they're looking really good! The formwork was set for the driveway and front path, ready for concreting tomorrow. I spent a bit of time breaking my back by getting the weeds out of the top tier of the retaining wall, so it's ready for some soil improvement and plants. The cabinet maker came out to measure up the space in the laundry, so hopefully that will crack on soon as well.
This is what i arrived to see - what was meant to be the concreter meeting to discuss things before they started later, and solar people not arriving for another 30 mins, instead I find it all in full swing!
Like ⋅ Add a comment ⋅ Pin to Ideaboard ⋅
Panels for hot water system getting lifted onto roof
Like ⋅ Add a comment ⋅ Pin to Ideaboard ⋅
The old hot water system is taken away
Like ⋅ Add a comment ⋅ Pin to Ideaboard ⋅
New hot water system is in and looking good!
Like ⋅ Add a comment ⋅ Pin to Ideaboard ⋅
Concreters getting stuck in to the kerb and footpath
Like ⋅ Add a comment ⋅ Pin to Ideaboard ⋅
Much more space down the side now the hot water system is gone
Like ⋅ Add a comment ⋅ Pin to Ideaboard ⋅
Like ⋅ Add a comment ⋅ Pin to Ideaboard ⋅
We'll be able to wheel a bin or barrow through there nicely now
Like ⋅ Add a comment ⋅ Pin to Ideaboard ⋅
Like ⋅ Add a comment ⋅ Pin to Ideaboard ⋅
Like ⋅ Add a comment ⋅ Pin to Ideaboard ⋅
Like ⋅ Add a comment ⋅ Pin to Ideaboard ⋅
About 14m of weeds to dig
Like ⋅ Add a comment ⋅ Pin to Ideaboard ⋅
All gone! Now to get the cultivator and some soil products up there
Like ⋅ Add a comment ⋅ Pin to Ideaboard ⋅
Front and side ready for the next round of concreting
Like ⋅ Add a comment ⋅ Pin to Ideaboard ⋅
Like ⋅ Add a comment ⋅ Pin to Ideaboard ⋅
The back and side paths were concreted today and they're looking really good! The formwork was set for the driveway and front path, ready for concreting tomorrow. I spent a bit of time breaking my back by getting the weeds out of the top tier of the retaining wall, so it's ready for some soil improvement and plants. The cabinet maker came out to measure up the space in the laundry, so hopefully that will crack on soon as well.
This is what i arrived to see - what was meant to be the concreter meeting to discuss things before they started later, and solar people not arriving for another 30 mins, instead I find it all in full swing!
Like ⋅ Add a comment ⋅ Pin to Ideaboard ⋅
Panels for hot water system getting lifted onto roof
Like ⋅ Add a comment ⋅ Pin to Ideaboard ⋅
The old hot water system is taken away
Like ⋅ Add a comment ⋅ Pin to Ideaboard ⋅
New hot water system is in and looking good!
Like ⋅ Add a comment ⋅ Pin to Ideaboard ⋅
Concreters getting stuck in to the kerb and footpath
Like ⋅ Add a comment ⋅ Pin to Ideaboard ⋅
Much more space down the side now the hot water system is gone
Like ⋅ Add a comment ⋅ Pin to Ideaboard ⋅
Like ⋅ Add a comment ⋅ Pin to Ideaboard ⋅
We'll be able to wheel a bin or barrow through there nicely now
Like ⋅ Add a comment ⋅ Pin to Ideaboard ⋅
Like ⋅ Add a comment ⋅ Pin to Ideaboard ⋅
Like ⋅ Add a comment ⋅ Pin to Ideaboard ⋅
Like ⋅ Add a comment ⋅ Pin to Ideaboard ⋅
About 14m of weeds to dig
Like ⋅ Add a comment ⋅ Pin to Ideaboard ⋅
All gone! Now to get the cultivator and some soil products up there
Like ⋅ Add a comment ⋅ Pin to Ideaboard ⋅
Front and side ready for the next round of concreting
Like ⋅ Add a comment ⋅ Pin to Ideaboard ⋅
Like ⋅ Add a comment ⋅ Pin to Ideaboard ⋅
Looking good Taco !
Damn. If the gas was on the opposite side you'd have a massive of side access. You still have heaps though. Enough to roll the mower to the back yard!