I've decided to start a new thread and put the last two years behind me. My build permits have been issued at last and I'm looking forward to building my new house over the next 6-8 months.
To everyone else, hi I'm Dawn! I'm a 29 y.o woman building my first house.
I purchased land in stage 3 of the Ascot estate, Pakenham in July 2014. My land is 294m2 (10.5x28m). Titles for stage 3 were released February 2016, after a 10 month delay.
I'm building with a small custom builder that I engaged October 2014. I signed the building contract on the 15th of March 2016.
Progress of Build
22/07/2014 - Holding Deposit Paid on Land
18/08/2014 - Land Deposit Paid
28/10/2014 - Build Quote & Holding Deposit Paid
14/02/2015 - Colour Selection
11/02/2015 - Settlement
15/03/2015 - Build Contract Signed
31/03/2016 - Build Deposit Paid
23/09/2016 - Build Permits Issued
01/10/2016 - Build started
13/10/2016 - Slab down
18/10/2016 - Frame completed
4/11/2016 - Bricks going up
14/11/2016 - Lock up completed
19/11/2016 - Bricking completed, hob in, insulation going in
13/12/2016 - Fixing stage completed
14/06/2017 - Garage door on
21/6/2017 - Gas line installed/front fence going up
30/6/2017 - Render
19/7/2017 - PCI
11/8/2017 - Handover
aloenyx