Hi all, I've lurked long enough now I'd feel bad if I didn't put up a thread for our build so here goes.

Bit of background, the wife & I had been looking to buy a house for a while with the main requirement being that it had to be within 30-40 mins commute to Sydney CBD and on at least a 700sqm block with decent frontage. After seeing many houses and many auctions and the prices people were asking for something that just wasn't going to be exactly what we wanted she finally found a house she absolutely loved but it was in Kellyville which pushed the travel time out just that little bit too far.


14th April 2018 - We went to see the house in Kellyville (3 Farmhouse Avenue for those interested -https://www.realestate.com.au/sold/property-house-nsw-kellyville-128012882) and fell in love with it. The front landscaping was nicely done, they hadn't really done anything with the backyard, but wow the house was just ticking all our boxes ... maybe it was the fantastic interior designer job they had done on it, the massive master suite, who knows, ultimately the finish was top notch in our books.

So this is the house that started our Rawson inspiration -



Here's some pictures I found of the interior later on a home styling blog - https://www.adoremagazine.com/home-tour ... atedwarmth

Now, we just had to find a way to move the house a little closer to the CBD ...

The agent that was selling the house told us it was built by Rawson Homes so after we went to see the house we wanted went to see Rawson Homes at the Kellyville display village just down the road to tell them of our plans. We looked through all the display homes they had, booked in an appointment to sit down with a salesperson the next weekend and then also took a trip out to the Homeworld at Leppington to look at the Chifley they had there.


21st April 2018 - We went to see a property that was for sale in Baulkham Hills, very different proposition but it was on a flat corner block with just a little over 700sqm and 18m frontage -



Perfect, we walked around the block and it seemed to tick all the boxes, nice quiet wide street to boot and we just needed to buy it and then work out what to do with the house later. I don't think we actually set foot in the house as we had a plan and nothing was going to stop us, what could go wrong?!

The house had passed in at auction the previous weekend and after some negotiation and sticking to our guns despite the owners asking for more and other offers trying to match our initial reasonable offer coming in, our offer was accepted on the 26th April 2018. We agreed on a 3 month settlement so we would have time to try and work out all the house side of things and this worked for the current owners who would like their children to be able to finish out the school year at their current school if possible. As it was likely going to take more time to sort the house out we also agreed to rent the house back to the current owners for at least two months and then monthly ongoing after this. Ok, we have a block of land with a house we don't need, time to get back in touch with Rawson Homes.


28th April 2018 - We met with Hennie Roos at Rawson in Kellyville and he was great, took us through all the different plans, gave us what we needed to started and even printed us off some full size flipped plans so we could play around with drawing up the modifications we would want and come back to him to get an idea of what sort of cost we'd be looking at.

Below is the list of the main items & modifications we asked for and the rough pricing Hennie provided for these things -


Item Price
Chifley 42 Classic with LUX Inclusions (price is subject to change on the 1st May)$ 444,600
Estimated Site costs$ 70,000
Luxury Redefined Promotion$ 5,000
Garage Extension with 5.2 opening (not quite triple)$ 8,000
Extended Alfresco full width (includes slab & roof)$ 11,000
Family room extension inc. tiling$ 7,500
Extension 1st Floor BR3 including carpet$ 7,400
Island bench custom$ 5,000
Butlers Pantry$ 11,000
Rock wool between ground & 1st floor$ 1,200
Sound screen insulation around a cinema or room$ 1,200
2 x cavity sliders $ 980
1 x hinged door$ 360
Gas Point$ 380
Water point to Fridge space$ 380
Tiles smart waste outlets$ 1,250
Ceiling to cornice height tiling for 4 x bathroom$ 8,000
Higher vanities throughout $ 1,000
Bi Fold Door to Alfresco$ 5,500
Glass Balustrade to staircase$ 9,000
Bi Fold WIndow t Kitchen$ 4,000
Additional cabinetry to WIR Bedroom 1$ 1,000
Extra hinged door to BR 4$ 380
Swap bathroom Shower & Wc – combined wet area – no charge
Roller door to rear of garage$ 900
2600mm high ceilings to ground floor in lieu of standard 2450mm$ 5,500
Electrical allowance$ 5,000
TOTAL$ 615,530



29th April 2018 - We sent back a completed application form and paid the $1,200 deposit to Rawson Homes to lock in the current pricing and so the site survey & soil test could be arranged. Below is the standard Chifley 42 Plans we started with -




24th May 2018 - After going back & forth with Hennie on the different modifications & upgrades we'd like to make we ended up with the following "final" marked up plan -



We were given the following updated rough idea / estimate of costs by Hennie -

Chifley 42 LUX with Classic Façade$ 444,600
Site costs, council costs $ 70,000
Demolition Allowance $ 30,000
Luxury Redefined $ 4,990
Plan Changes & extensions$ 59,500
Non standard Variations$ 33,760
Display Home Upgrades$ 33,055
Electrical Allowance$ 5,000
TOTAL$ 680,905


We signed everything off so that our tender could start being prepared.

5th June 2018 - Our broker said that the Rawson payment schedule is rather front loaded with 25% at Slab Pour and that this may cause issues. We spoke with Hennie and he said he's sure something can be sorted out down the track to appease the bank.



This is what our broker provided as a more normal / acceptable schedule, would appreciate any wisdom people have here as I have no idea who to believe -



The response we got from Hennie seems to be pretty generic, again interested in others opinions on this -

"Rawson Homes is one of the largest builders in NSW. We have spent a lot of time calculating the costs that we outlay at each stage to ensure that we are not out of pocket when having to pay for materials and labour. The most costly stages of a build are slab, frame and brickwork. Before we even commence works on site, we have spent in excess of the $15,000 (5K Tender Acceptance & 10K Contract Signing Deposit) for a Knock Down Rebuild which has been paid by the client. This is a common occurrence for builders, due to the increased expense associated with council application fees, home owners warranty and expert reports (engineering, surveying, geotechnical etc).

We also carry out an annual review to ensure that on average across the houses that we have construct we cover the costs incurred whilst not charging too much. We can appreciate the banks position, but also we need to ensure that we are not taking on too much risk.

With this large volume of homes, the vast majority of banks accept our progress claims schedule without amendment. On the small percentage who require a change, the only change that is required, is to shift 5% from the slab claim to the frame claim.

You can request this variation with your Pre Construction Administrator after Tender Acceptance during the “Pre-Construction Process”


10th June 2018 - We received an email from Hennie telling us about the new "Unwrap your way to $70k" promo Rawson are doing compared to the "Luxury Redefined" promo. Basically it would mean the price of the Chifley 42 Classic would go up to $456,300 (compared to $444,600 previous pricing) and the "Unwrap your way to $70k" promo is $9,990 (compared to $4,990 with the "Luxury Redefined").

Had to do some thinking on this one but ultimately as the "Unwrap your way to $70k" would include a lot of extras we wanted it seemed to make financial sense to go for it so we agreed to the change. We are still going with the "Energy Saving Bonus" which gives the Tesla Powerwall, Inverter and Solar panels, etc, but decided not to go with the "Street Appeal Bonus" as there didn't seem to be any tiles or bricks that we particularly liked more than the standard


18th June 2018 - We received an email to book in our tender presentation and booked in for the 5th July 2018.

5th July 2018 - The tender presentation went pretty much as we thought it would and was great to also be able to look through a lot of the internal choices (eg. different tiles, taps, sinks, toilets, etc) at the Rawson head office showroom as we got there a little early so had a wander around. After getting some clarifications from our tender presenter (Gerry Fochesato) we signed the tender and paid the $5,000 deposit so things could continue.


6th June 2018 - Got some bad news about our proposed "almost 3 car" garage, going to have to reduce it to barely over a 2 car garage because we are on a corner block that is only just over 18m wide. We were very specific about wanting the bigger garage from our first discussions with Hennie so it's a bit of a pain this has only come up now ... there goes the idea for putting in racks for storage on the side of the garage




12th July 2018 - We received our "Tender B". I'm going to put this information here because when we were looking at other Rawson builds and trying to work out how much certain things we wanted would cost we couldn't really find any clear information so hopefully this helps someone if they're looking at similar modifications / upgrades. Sorry if it's a bit of a dog's breakfast.

Also I'd be interested to know if anyone else with more experience thinks we're getting ripped off on anything or if there are perhaps items we should remove and get done through separate contractors after we're in the house.

SITE COSTS

DEMOLITION & SITE CLEARING

SITE PREPARATION
CONCRETE SLAB
WATER CONNECTION
ELECTRICAL CONNECTION
SEWER CONNECTION
PIERING TO SLAB
STORMWATER CONNECTION
GAS CONNECTION
DRIVEWAY
RETAINING WALLS
TELECOMMUNICATION CONNECTION
WIND CLASSIFICATION
ACCESS FOR CONSTRUCTION

TOTAL SITE COSTS: $88,705

AUTHORITY CONDITIONS
CDC BUILDING REQUIREMENTS
AUTHORITY BUILDING REQUIREMENTS

TOTAL COUNCIL CONDITIONS: $3,140

CLIENT VARIATION REQUEST

PROMOTION


40th Anniversary Promotion 1 - UNWRAP YOUR WAY TO $70K*

$9,990

PLAN CHANGES

-= GROUND FLOOR =-

Provide approximately 5980mm (L) x 830mm (W) extension to Garage towards side boundary, provide approximately 5200mm (W) Garage opening including Panelift Garage door to suit;
$3,660

Provide approximately 1960mm (L) x 600mm (W) extension to Ground Floor Powder towards side boundary, including reconfiguring as per sketch, provide one x additional Lux standard Shower with standard tapware to suit, provide one x aluminium sliding window to suit;
$6,075

Reconfigure Dining, Lounge and Theatre as per sketch, including rename Theatre as Study, provide one x 2340mm (H) x 820mm (W) flush panel hinged door in lieu of standard opening to Study, rename Lounge as Theatre including provide two x 2340mm (H) x 720mm (W) flush panel cavity sliding doors with platinum 3000 cavity sliding door pockets to suit in lieu of standard opening
$1,820

Reconfigure Kitchen as per sketch including delete standard Butler's Pantry and Walk in Pantry, provide new sink run along rear elevation including underbench cupboards to suit;
($1,690)

Provide Butlers Pantry to previous Dining room (refer Seaview 36 Display at Homeworld V as a guide only), including approximately 2800mm (W) 40mm Standard range Caesarstone benchtop with underbench and overhead cupboards to suit, provide one x aluminium fixed splashback window in lieu of standard, provide single Clark Monaco undermount sink including Stylus Venecia mixer tap including polishing of Caesarstone to suit, provide approximately 2800mm (W) laminate tall unit Pantry to opposite wall; and
$11,385

Provide approximately 4590mm (L) x 1290mm (W) extension to Family towards side boundary, aligning with Laundry to suit.
$5,285

-= FIRST FLOOR =-

Provide approximately 4590mm (L) x 1290mm (W) extension to Bedroom 3 towards side elevation to suit extension below, relocate BIR to side elevation, relocate Bedroom 4 BIR to Bedroom 3 to suit, extend Bedroom 2 WIR and Linen to suit previous BIR space;
$ 5,410

Relocate separate WC to Main Bathroom, relocating Shower to suit;
($ 250)

Provide approximately 500mm (L) x 3720mm (W) extension to Bedroom 5 towards front boundary, reducing Lounge to suit; and
Note

Provide approximately 1100mm (L) x 6790mm (W) extension to Bedroom 1 towards rear boundary, reducing Lounge to suit and reducing void to suit.
$750


-= NON STANDARD VARIATIONS =-

Provide upgrade to 'Daikin' Premium Inverter 20KW ducted air conditioning with two zones in lieu of 14KW Standard Inverter, due to house over 35 squares

Included

Provide two x additional air conditioning zones
$900

Provide 2040mm (H) x 820mm (W) flush panel cavity sliding door in lieu of standard opening to Bedroom 1 Ensuite
$450

Provide 2040mm (H) x 820mm (W) flush panel cavity sliding door in lieu of standard to Bedroom 1/Bedroom 4
$450

Provide one x aluminium fixed corner window (AFW1625SP/AFW1630SP) in lieu of standard to Family (refer closed Chifley 42 display at Gledswood Hills as a guide only)
$1,450

Delete BIR's to Bedroom 1 (Client to install fitout after handover)
($ 1,020)

Provide R2.5 Soundscreen insulation to between floor joists (Living areas only, excludes over Garage)
$4,380

Provide approximately 950mm (H) vanities throughout dwelling
Note

Provide 10mm fully frameless Shower Screens in lieu of standard semi-frameless throughout dwelling
$5,220.00

Provide one x external gas bayonet point to Alfresco
$380

Provide solidcore flush panel hinged door in lieu of standard to Garage internal access
$160

Provide R2.5 Glasswool insulation to Garage and Alfresco ceilings
$695

Provide a capped off cold water point to fridge space
$380

Provide 60mm Standard range Caesarstone in lieu of 'Promotion' 40mm to Kitchen Cooktop run and 1200mm (W) x 2000mm (L) Island Bench including two x waterfall ends
$3,675

Provide approximately 950mm (H) Kitchen Cooktop run and Island Bench in lieu of standard
Note

Provide 40mm Standard range Caesarstone benchtop in lieu of 'Promotion' laminate benchtop to Laundry fitout
$545

Provide 2100mm (H) Stegbar framed mirror sliding robe doors in lieu of two x standard hinged doors to Bedroom 5 BIR Note: Minimum 1200mm (W) opening
$350

Provide standard range ceramic floor tiling (selected from Rawson Homes extensive range) in lieu of broom finished concrete to Porch.
$435

Provide concealed leaf guard protection to standard gutter and valleys
$4,325

Provide one x additional garden tap to rear of dwelling
$380

Provide single colorbond roller door in lieu of standard range facebrick to rear of Garage
$800

Provide one x aluminium bi-fold door (ABW2427-3) in lieu of standard to Family/Alfresco, including recessed sills to suit
$2,915

-= DISPLAY HOME UPGRADES =-

Refer to Chifley 40 Display at Emerald Hills as a guide only 26 Provide Square set ceiling junctions to Ground Floor and First Floor
$3,990 throughout

Provide Gainsborough Angular passage and privacy sets (Code: 1800ANGSC & 1805ANGSC) in lieu of standard throughout dwelling
$275

Provide Feature aluminium fixed window (AFW772x2410SP) with no bottom reveal in lieu of standard to Office
$55

Provide Feature two storey plasterboard niche including full height vertical Cedar shiplap cladding (78mm x 26mm) (Stain finish as selected) in lieu of standard to Hallway including 180mm framed wall to suit.
$2,930

Provide aluminium awning window (AAW2424SP) with no bottom reveal in lieu of standard to Lounge
$195

Provide Two x Hafele No.15 pull out unit with Loox lighting strip in lieu of standard cabinetry to Cooktop run
$620

Provide Full height laminate overhead cabinetry in lieu of standard to Cooktop run and Pantry
$1,020

Provide One x Hafele concealed drawer to Cooktop run
$180

Provide Aluminium fixed window (AFW2306) with no bottom reveal in lieu of standard to Pantry
$55

Provide Aluminium fixed window (AFW2318) with no bottom reveal in lieu of standard to Family/Dining
$210

Provide Recessed slab setdowns in lieu of standard to Ground Floor wet areas
$600

Provide Full height ceramic wall tiling in lieu of standard to Ground Floor Powder
$1,995

Provide 300mm Caesarstone apron in lieu of standard to Ground Floor Powder Vanity
$890

Provide Recessed wet areas to First Floor in lieu of standard Drafting Note: Highlight recessed wet areas
$1,050

Provide 140mm Caesarstone apron in lieu of standard to two x Bedroom 1 Ensuite Vanities
$1,230

Provide 140mm Caesarstone fascia in lieu of standard to Main Bathroom Vanity
$680

Provide Full height ceramic wall tiling in lieu of standard to Bedroom 2 Ensuite
$1,995

Provide NX8 Series alarm system with three sensors, including single power point and additional phone point.
$1,290

-= PROVISIONAL ALLOWANCES =-

Provide allowance for Staircase upgrades: PROVISIONAL ALLOWANCE

$7,000

Provide allowance for Tiling upgrades: PROVISIONAL ALLOWANCE
$3,000

Provide allowance for Electrical upgrades: PROVISIONAL ALLOWANCE
$5,000

Provide allowance for Kitchen Servery upgrades: PROVISIONAL ALLOWANCE
$2,500

Provide allowance for Under Tile Heating upgrades: PROVISIONAL ALLOWANCE
$4,000

Provide allowance for Internal Wall insulation upgrades: PROVISIONAL ALLOWANCE
$3,000

TOTAL CLIENT VARIATION REQUEST: $107,845

SUMMARY

Package Price: $456,300
Additional Site Costs: $88,705
Additional Authority Requirements: $3,140
Client Variation Request: $107,845
Tender Fee Paid: -$1,200

The total cost to construct is: $654,790


16th July 2018 - Had previously contacted McDonald Contracting, a company specialising in moving homes to see if there was a possibility of someone perhaps wanting to buy the house on the block. Turns out they can have a chap pop around tomorrow to look at the house and check things out but the person I spoke to in the office thinks the house is lovelly and wouldn't have any troubles finding someone who would want to buy & move it.


17th July 2018 - In good news settlement of the property went to plan and we now own the house & land, in bad news McDonald Contracting says the house is too big and that they would never get approval (assume from council?) to move it. Very strange as I had provided them with the address and real estate ad for the house showing pictures and the plan so I'm not sure why they initially would have even said it was possible or sent someone out to look at the house without looking at that information first - oh well, plan B .... Does anyone know a good demolition company in Sydney that also does some salvage to try and keep the demolition costs low!?!

23rd July 2018 - We have been contacted by our pre-construction administrator at Rawson (Simone Brummell) who advised our file is with drafting to begin on our application plans. Once these are ready we'll have our plan presentation and the external colour variation meetings which should take about half a day for both meetings.

There was also a note about a drafting variation so will be interesting to see what this is for.

31st July 2018 - We received our application plans from Rawson and booked in our plan presentation for the 16th August 2018. All of a sudden we realised that although we've been out to Austral Bricks & PGH to look at tiles and bricks we haven't actually deciding on everything such as the front door, timberwork, driveway colour, cladding colours, fascia, gutter, downpipes, rainwater tank, window frames etc .. Crud, looks like we'll have some busy weekends ahead of us to make sure these things are locked down.

8th August 2018 - We received the drafting variation from Simone at Rawson, looks like a slight change to the site preparation, slight change in some windows needed but a big one is they seem to have not included the bifold windows from the kitchen to the alfresco in any of the original costings despite this clearly being requested multiple times and on all the plans (even the application plans we were sent had the bifold windows on them!?)

Do we have any recourse on this seeing as we have already signed a tender that should have included this or basically is it a case of it doesn't matter if they were depicted on the plans, if the cost was left off the tender due to an error on Rawson's part either we have to just cough it up if we want it or if we don't it's a case of too bad, no bifolds then?




10th August 2018 - That basically brings everything up to date so a busy weekend ahead of finalising all the external colours and getting this information over to Rawson before our plan presentation meeting on Thursday next week.

Based on a suggestion from KateAndDuke in another thread I've spent the best part of the nights this week modelling up the house in Live Home 3D (http://www.livehome3d.com) so I could play around with the external bricks / colours, etc so I will post up some images of the different combinations we're thinking of but unfortunately even though I've used the images from Austral Bricks & PGH websites specifically for 3D modellings I think the way the bricks look in real life / different lights will likely be very different so will really have to try and make sure we see lots of houses with the different combinations on the weekend.

Still needing to find a good demolition company in Sydney, preferably one that also does some salvage to try and reduce the cost as they house we need to get rid of was only recently renovated so a lot of the internals should be good
If anyone has any recommendations please let me know.

Similarly if anyone looks over the costings in our tender above and thinks there is anything we should scrap from the Rawson build and get done later after completion as it will be cheaper please let me know, always looking to save $$$$$.

This is my first build post so if I've done anything wrong or posted up any information I shouldn't have please also let me know and I'll edit it out. Thanks in advance, hope people find this useful and looking forward to hearing any suggestions everyone has.
Wow mate. How did you get all that done in this bloody website that refreshes all the time. I wish they would just turn that feature off.
A couple of things. Congrats first off. 2nd reading your thread is like ground hog day for our dealings with rawson. All I can say is check everything and check it again. There is obviously no communication between drafting and the sales team. Our alfresco was reduced in size and we never got a reason for it other than building constraints. So id question them on the garage. You have a big frontage so I can’t see why it can’t be done.
Check your variations thoroughly as similar to you we had things taken out and things such as the void as you enter the house filled in. 😳. We since found out that the plans Head offshore. So who knows whose doing them.
We found pricing on appliances and taps etc pretty competitive but we have chosen to to our walk-in robe after handover.
Wow what a opening post!


So many Chifleys being built now!

We found all the initial costings as part of the tender process were pretty reasonable. It wasn't until we did selections that we became suss to a few things such as it costing $4,000 for soft close cupboards in our butlers kitchen we added because "That's the fee we charge to add soft close to a kitchen" which meant over $200 per a door, there weren't even any drawers. This came down to under $400 in the end so it was worth asking about. Then there was some double charging for things we had in our initial tender but replaced in selections. Overall Rawson are way more reasonable than Mojo/MJH who we were going to build with and came to over $100,000 on selection day especially as it felt everything had to be upgraded because their standard was cheapest of the cheap.

Plan presentation is fun! Just a word of caution though, make sure you have an openable window in every "room" our study, dining and media room aren't closed but their still classified as individual rooms by basix and they have fixed windows. Our dining room is the best example of how stupid this rule is because there is nothing seperating it from the living room which has a sliding door and louvre window in the kitchen which again isn't seperated from the dining room but still needs an openable window... It doesn't seem to apply to bathrooms and Laundry though.

Looking foward to seeing your progress!
Not building with rawson but we planning a similar build do very interested in following your build! Good luck!


Hi Huhness

Dropped into your blog and, to my delight, saw that your build is in Illawong. Mate, you guys have chosen just the best Sydney suburbs to live in. We've just moved on after 30 years of living there - to build our last home on acerage - and enjoyed every moment of living in 2234. The location, the topography, the people just make Illawong a hidden gem. You can tell we liked it


Anyway, just thought you might find a couple of GrandDad inputs useful to your build:

Termites.

A real problem in the suburb. Whatever termite system you've planned to put in, double it. Essential to maintain the concrete slab edge completely clear so that you can monitor for intrusion. No garden, no mulch, no water tanks, no dripping wall-mounted taps, up against the house. It's a pain in the bum but annual termite inspection is really a must.

Bush Fire

It will happen. It it isn't fun. Whatever BAL you've got, think about metal window screening and ember intrusion. We locals all learnt a lesson when 2 Alfords Point homes went up, it's not just the flame front, it's the embers. Keep gutters clean; owners don't seem to have much success long-term with gutter guard systems.

If I was building in Illawong again, I'd consider a couple of professionally mounted roof sprinklers. With a pool installed, I'd think about a fire-pump.

Building Supplies

You owe yourself a whiz up to Trademaster in South Granville in the next few month. Their hardware, building product range and prices are just unbeatable. And the team there are simply ace.

Garden Stuff

As you work on your landscaping a visit to Rockdale Community Nursery will surprise you. Great range/prices on plants and all looked after by a team of intellectually challenged adults....lovely people.

Really looking forward to reading you blog and sharing your building journey.

PS Enjoy the Illawong Chinese Restaurant, we miss it.
Thanks for the feedback guys, thankfully I don't seem to have any refresh issues when I construct posts but I write them in a separate reply window rather than using the "quick reply" bit at the bottom of the thread, not sure if that's it?

Definitely going over everything with a microscope now when it comes to what we've asked for. What's slightly annoying is when we've asked for extra things to be included previously (eg. heated floors in bathrooms, sound insulation in certain areas, etc) we've been told "yes, yes, that can be done at a later meeting" but then it seems like they have not noted down these things we've already requested, so it's really on us to make sure we bring them up again at whatever meeting they deem appropriate otherwise they'll likely be left off.

Will have to keep an eye on those soft close cupboard costs Huhness, wowsers! It does worry me that sometimes it seems when you ask for something in place of something else they don't seem to factor in the cost of not providing whatever the standard item was , and instead you just have the cost for the replacement item with no credit for the thing you're not getting.

11th August 2018 - We went out to PGH & Austral Bricks again on the weekend (as well as driving around 30+ homes in Colebee, a nearby new land release with lots of new homes recently built, to see the bricks on actual homes in "real" natural light) to try and finalise our external colour selections and I think we've decided ... well hopefully as my wife is sending them off to Rawson in preparation for our Plan Presentation on Thursday.

Australia Bricks was definitely a better colour appointment and they were far more helpful in going through everything and giving feedback on different options we were considering. PGH basically just took what we said and put it on a display board, but they were not very interactive with ideas on what might look better and didn't really give any feedback. We we're still on the fence about whether to go for the Gibson brick from PGH or the Freedom brick from Austral Bricks, but in the end have decided on the Freedom and I think the experience at the colour appointment may have swayed us.

We were also originally going to go a wood look garage door to match the wood in the pergolas and the front door, but after not seeing a single house where they have been able to match the colours in the garage door and the front door (they're always slightly different, in some cases glaringly and it's not a good look!) we've decided just to go colour.

Here's the colour selections we ended up with at both brick yards -

PGH

Roof Tile - Monier Atura, Barramundi
Bricks - Desert, Gibson
Mortar - Off White, Ironed
Gutters, Downpipes - Colourbond Monument




Austral Bricks

Roof Tile - Monier Atura, Sambuca
Bricks - Everyday Life, Freedom
Mortar - Off White, Ironed
Gutters, Downpipes - Colourbond Monument
Garage Door - Nullabor Woodgrain Texture, Colourbond Monument
Front Door & Pergola Timber - Quantum Stain, Walnut
Primeline Boarding (first level on the left side of front and right side of rear) - Taubmans Stonebridge
Fibre Cement Sheeting (above the garage) - Taubmans Wallaby
Eaves - Surfmist
Driveway - Avista, Gunmetal






As you can see, pretty similar selections but as mentioned Austral Bricks went into far more detail and discussed things that PGH didn't even ask about such as the driveway colour and eaves.

I then mocked up some 3D renderings of what the house should look like but unfortunately despite using the colours and textures from the suppliers websites I still don't think they look close enough to how the colours will look in real-life (eg. the wood stain was very hard to try and replicate as a texture, and the monument colour looks darker in real life), but I guess gives a good enough indication of what we were going for with the different tones used in various locations, etc.

Front


Left Side


Right Side


Rear



Interested to hear anyone's thoughts on our colour choices! Next step is to model up the kitchen and butler's pantry fitout in 3D to make sure we're happy with the look, will keep you posted.

Also still really need to sort out our demolition so if anyone has any recommendations of Demo companies in Sydney I'm all ears.
Great overview JiMb00 - it's looking great
Looks great!
We are currently in Kellyville (built 6 years ago, border of Bella vista) love the proximity but we don’t need to go into the CBD.
Built in Baulkham hills many years ago...
hi Jim, I am also building the Chifley 42 as well with a classic facade, could you please let me know how much did you pay for quantum walnut colour for the pergola? Thank you. Looking forward to your updates as well. Very good post!
Monica.zhen
hi Jim, I am also building the Chifley 42 as well with a classic facade, could you please let me know how much did you pay for quantum walnut colour for the pergola? Thank you. Looking forward to your updates as well. Very good post!

Hi Monica,

Sorry for the delay in reply as things have been a little hectic with finalising everything to move the build forward and my wife is now 27 weeks pregnant with twins but on bed rest so I'm finding out what it's like to have to do all the little jobs on my own that couples usually share between themselves.

I don't believe we had to pay anything extra for the quantum walnut colour for the pergola but I might be wrong. I've looked over so many different numbers in the contract and variations I'm getting a little blind to it all now unfortunately. Looking at our contract is just says "Provide corner façade treatment to side of Living, blah blah blah, face brick piers and painted timber pergola over". We had to get this because we're on a corner block so they said it couldn't just be a straight wall and had to have an "architectural feature" to break it up.

In good news our build is all a go so without further ado I'll upload some pictures now in some separate posts of the visits and progress. Will hopefully be able to keep this thread updated a little more frequently!
18th November 2018 - Pre-demolition:


Sold as much of the plants & stuff inside the house that I could, pretty much everything went except for the light fittings & fans. These shots were taken before much had been taken / picked up so probably the best "start" shots





25th November 2018 - Demolition (Internal Strip Out):

Went with Eco Demolition (https://www.housedemolition.sydney/) and couldn't be happier. Charlie & Michael are absolute gentlemen and I can't recommend them highly enough. If you need demolition in Sydney, these are your guys!


























8th December 2018 - Demolition (House & Concrete Removal with Excavator):

We had a ton of concrete up the side & the back of the property but it wasn't a problem for the lads at Eco Demolition!









10th December 2018 - Demolition (Site Cleared):

Look at the beautiful clear block, the little orange excavator did us proud! Thanks again to Eco Demolition as I don't think we could have asked for the site to be left any clearer / neater / level.


During the demolition process we were also told by Rawson that we would need to arrange with council for certain trees to be removed from the nature strip because of where the driveway for the new house is to be located. Originally the plans indicated only one of the trees would need to be removed so we arranged this with council, only to then be told by Rawson a week later after having that tree removed that we would need to remove another one because it would be too close to the driveway and they wouldn't be able to get on site until the second tree was removed … just like everything with Rawson so far, nothing is easy and why tell us to get council to remove two trees at the same time when you can annoyingly space it out, delay progress and make us go through the whole tree removal request process with council again. FML.







Good to see progress guys. If I have learnt anything, you need to keep an eye on the build and don’t be afraid to ask questions.
28th January 2019 - Watching Grass Grow, literally:

So we got stuck in the Christmas / New Years shutdown because Rawson couldn't get the final kitchen plans right multiple times. Despite when we went in for our internal appointment me telling the staff member I had already mocked up a 3D Render of the kitchen & butlers pantry with dimensions for everything which I could email to her she said "That's nice, but I'll just talk to you about it instead and make my own notes if that's ok". In the end we got the hurry up because our internals / kitchen appointment was booked in the morning and our tiling appointment was booked in the afternoon so we had to go to that.

It's worth noting the person you speak to at Rawson isn't by any means a kitchen specialist so there were lots of questions she simply didn't know the answer to. as you can imagine when the kitchen plans first came back everything was not as we thought we had asked / what we wanted, if only there had been some way of visually knowing what we wanted at the start with dimensions clearly stated, etc ... shame noone offered to give that to Rawson, oh wait, I did!?




8th February 2019 - Rawson on Site (Peg out, change of fencing & a loo):

Finally things are a go with Rawson, we could breathe a sigh of relief and give let the poor guys at Eco Demolition take back their temporary fencing which they had been letting us keep until Rawson took over the site.

Our site manager is Neil Conen and I've heard that once you stop dealing with the Rawson office staff things go a lot smoother / you don't get as much brain damage so here's hoping as I feel like I've had a frontal lobotomy with the amount of re-work and emails going back & forth in the paperwork stages.










16th February 2019 - Slab Formwork Done:


Looks like a lot of polystyrene to me but what do I know about waffle pod construction?! The answer to that question is not much, so if anyone can see anything they think was done wrong please let me know but unfortunately everything went so quickly we didn't have time to arrange an independent pre-pour slab inspection



















18th February 2019 - Slab Pour:

Look at all that sweet sweet concrete being pumped in!! Not sure how I feel about all the guys throwing their ciggy butts and hawking up big slags and spitting them into the slab where they stood whilst I was clearly there as the owner having a sticky beak, so sometimes it's better just to see the end result that the work in progress where tradies are involved.

They were having some big issues when we were there as the pump kept getting clogged and they were pulling some pretty sizeable chunks of dried concete out of the gate they have between the concrete truck mixer and the pump truck, you can see a massive piece in the 3rd last picture below behind what looks to be an old football.















24th February 2019 - Slab Complete:

We have a slab! Would be interested again in hearing anyone's thoughts on a few things as we got an independent post-pour slab inspection report for the slab and the only issue it mentions is that there appears to be a slight dip between bed6/study and the home theatre room where the slab is not level and this is evident by the water that has been pooling in that area after recent rain.

We brought this up with our site supervisor and he said if there is more than a 4mm variance they'll sort it out with a self levelling concrete (Ardex?) before doing the floor coverings, but I'm wondering how they'll do that as then there will be a frame / wall in then and the dip is in between two rooms



Also other things we noted which the neither the inspector or site supervisor seem to worried about are things like -

* North East Corner - Corner of slab chipped off and slab incomplete in areas near the ground

* Middle of slab - Recessed slab edge appears rough and not consistent with the other edges. Also waste pipe in the middle of the recessed edge.

* Eastern side of slab - Edge appears very rough / chipped away in places

* Front of slab - Corners rough and slab appears incomplete near ground
* Southern edge of alfresco - Slab appears incomplete near ground with things poking out from edges

* There seems to be a lot of concrete left around the site, is this normal?










































Related
24/02/2024
0
Building in Vineyard with Rawson

Building A New House

Just started the Build process for Chifley 42 with Rawson homes, will keep you all posted with the Build progress.

11/05/2023
1
Building duplex at the hills council area

Building A New House

Even if it's not being sub-divided and you want to keep it as Torrens title, you will still need to talk to a town planner or Council themselves, to see if they will allow…

5/02/2024
4
Pool Builders, in and around The Hills Greater Sydney

Building A New House

Thanks again Simeon for being so elaborate. Appreciate it. Its gives us a very idea. Kind Regards

You are here
Building ForumBuilding A New House
Home
Pros
Forum