Browse Forums Building A New House 1 Dec 11, 2021 7:21 am Hi Does anyone know about Builders (in general) or AllCastle (in specific Builder) penalty to pay to us if the completion delay by x period ? How much the penalty if any ? I guess Rawson pay $250 per week if not compeleted over 8months ? (Correct me if Iām wrong) Thank you in advance for the info Re: AllCastle contract late completion penalty 2Dec 11, 2021 7:51 pm We are just starting out with allcastle. From memory, they have 48 weeks to build, plus any wet days, plus the shut down over Xmas. After that there is a fee, but it should all be listed in your contract. Re: AllCastle contract late completion penalty 3Dec 11, 2021 9:07 pm joshysaid We are just starting out with allcastle. From memory, they have 48 weeks to build, plus any wet days, plus the shut down over Xmas. After that there is a fee, but it should all be listed in your contract. Noted, I will check when sign the contract but geezzz, they allocate so much time, 48weeks, that more than enough Thanks Like I said the Occupancy Certificate is not the tollgate that marks the completion of the house. The contract defines… 7 10763 Hi we are looking to talk to people who have built with them recently. We have signed mid range built contract but identified that a lot of things are not included.… 0 745 Was the offer also on their website? If so, you could check the Wayback Machine. 1 1021 |