Browse Forums Building A New House 1 May 19, 2018 2:58 pm Hello, been following this forum for a while but thought I'd post up my build so other people looking to build with Easystart Homes (Summit) can get an idea of what to expect.
* Late August - Deposit paid on land * 31/08/17 - Signed PPA * 12/10/17 - Drafting Complete * 23/10/17 - Contract Signing * 03/11/17 - Planning Approval * 16/11/17 - Pre-Start Meeting * 24/11/17 - Estimating Complete * 05/12/17 - Drafting Complete * 12/12/17 - Finance Approval * 18/12/17 - Land Developer Approval * 02/01/18 - Final Plans Signed * 05/01/18 - Land Titles Issued * 25/01/18 - Land Settlement * 22/01/18 - Scheduling * 12/02/18 - Siteworks Complete * 14/02/18 - Slab Complete * 16/03/18 - Brickwork Complete * 13/04/18 - Roof Complete * 30/04/18 - Ceilings Complete * 07/05/18 - Plaster Set Complete * 14/05/18 - Lock up * 21/05/18 - Grano to Garage Complete * 23/05/18 - Painter - Spray * 25/05/18 - Ceramic Tiler Re: First Build with Easystart Homes - Perth 2May 19, 2018 3:02 pm Like ⋅ Add a comment ⋅ Pin to Ideaboard ⋅ Like ⋅ Add a comment ⋅ Pin to Ideaboard ⋅ Like ⋅ Add a comment ⋅ Pin to Ideaboard ⋅ Like ⋅ Add a comment ⋅ Pin to Ideaboard ⋅ Like ⋅ Add a comment ⋅ Pin to Ideaboard ⋅ Like ⋅ Add a comment ⋅ Pin to Ideaboard ⋅ Like ⋅ Add a comment ⋅ Pin to Ideaboard ⋅ Like ⋅ Add a comment ⋅ Pin to Ideaboard ⋅ Like ⋅ Add a comment ⋅ Pin to Ideaboard ⋅ Like ⋅ Add a comment ⋅ Pin to Ideaboard ⋅ Like ⋅ Add a comment ⋅ Pin to Ideaboard ⋅ Like ⋅ Add a comment ⋅ Pin to Ideaboard ⋅ Like ⋅ Add a comment ⋅ Pin to Ideaboard ⋅ Like ⋅ Add a comment ⋅ Pin to Ideaboard ⋅ Like ⋅ Add a comment ⋅ Pin to Ideaboard ⋅ Like ⋅ Add a comment ⋅ Pin to Ideaboard ⋅ Like ⋅ Add a comment ⋅ Pin to Ideaboard ⋅ Like ⋅ Add a comment ⋅ Pin to Ideaboard ⋅ Like ⋅ Add a comment ⋅ Pin to Ideaboard ⋅ Like ⋅ Add a comment ⋅ Pin to Ideaboard ⋅ Like ⋅ Add a comment ⋅ Pin to Ideaboard ⋅ Like ⋅ Add a comment ⋅ Pin to Ideaboard ⋅ Re: First Build with Easystart Homes - Perth 3May 25, 2018 2:02 pm Tiling has started this week. A couple of minor things with waterproofing where identified by the building inspector however these were quickly rectified by the builder. Like ⋅ Add a comment ⋅ Pin to Ideaboard ⋅ Like ⋅ Add a comment ⋅ Pin to Ideaboard ⋅ Like ⋅ Add a comment ⋅ Pin to Ideaboard ⋅ Like ⋅ Add a comment ⋅ Pin to Ideaboard ⋅ Like ⋅ Add a comment ⋅ Pin to Ideaboard ⋅ Re: First Build with Easystart Homes - Perth 4Jun 05, 2018 9:29 pm A few more things done on the house including the front being painted and power is now on. I've noticed they managed to put some of the wrong colour light switches and power points in so will have to inform SS about this. Like ⋅ Add a comment ⋅ Pin to Ideaboard ⋅ Like ⋅ Add a comment ⋅ Pin to Ideaboard ⋅ Like ⋅ Add a comment ⋅ Pin to Ideaboard ⋅ Like ⋅ Add a comment ⋅ Pin to Ideaboard ⋅ Like ⋅ Add a comment ⋅ Pin to Ideaboard ⋅ Like ⋅ Add a comment ⋅ Pin to Ideaboard ⋅ Re: First Build with Easystart Homes - Perth 6Jun 11, 2018 10:31 am Coming along quick! We started at roughly the same time (our slab 10/02) but I reckon you'll be done first! Re: First Build with Easystart Homes - Perth 7Jun 11, 2018 7:38 pm nicolac34 Coming along quick! We started at roughly the same time (our slab 10/02) but I reckon you'll be done first! At a pretty similar stage. My SS has estimated completion early July. Re: First Build with Easystart Homes - Perth 8Jun 18, 2018 12:50 pm Paving is now done and A/C installed. PCI booked for 9th July! hi guys. Please be nice. First time home builder in Qld. I would like some feedback please on whether I should build my granny flat first before my main house at the… 0 4589 So it looks like we finally have some movement on site! Definitely later than expected, but I'll take any progress at this point. I'll drop by over the weekend to get… 5 27721 11 41648 |