Browse Forums Building A New House 1 May 16, 2018 3:38 pm So we are nearly at 8 months since atart of build, 10 days over contract and just had the state manager come down from QLD to look at our house after we discovered a problem with our brickwork. The bricklayers have bricked in different mortor gauges so we have intolerances all over the house but the major one is on our back patio which is going to have to be pulled down and redone. However because the entire house has mortor gauge size issues they are suggesting we render the house. Where do we stand when it comes to compensation/building insurance? 8 months to get to this point is beyond ridiculous. We didnt want a rendered house. I just want to get it sorted so we can move in. First Home Buyer Building our first home in 2017 Ask the council if there is a chance of getting build over easement exemption. Sometimes easements are unused and 24cm is not all that much. Good luck. And yes any builder… 2 15203 ![]() Hi so sorry for the late reply. I already contacted them and they wouldn't tell me instead they tried to get me to talk to one of their home coordinators and I'm not… 2 6682 Just moved from a rental that was bearer and joist floor with double brick walls throughout. Worst house ever! Granted in Summer we didnt need any form of Air-Con to… 2 2801 ![]() |