Does anyone know what stages are most important to get it done by independent site inspector?
We also had a quote from Darbecca and we asked the same question! Whilst they said they were all important, they told us the most common inspections were:
1. Pre pour/ Steel inspections
2. Frame inspection (and complimentary slab inspection)
3. Pre plaster
4. Final Inspection
We're likely to do these 4 inspections. Fortunately, my father in law is an engineer so he's happy to help out with the other stages.
Thanks.
Fairhaven said that they will add 2 extra weeks to each stage if we hire independent inspector.
2 weeks isn't very long to make sure everything is done properly.
Bronte19 do you have a good understanding of how Darbecca work?
They come and check everything and write a report but how do we know Fairhaven have actually fixed those things properly?