OK so we are building in Lower Chittering in WA.
During our prestart discussions the builder advised they can do the power run in, temp db board and connection for just over 3k. We agreed.
We are doing our own site works. the site works quotation allowed a cost for the power run in which we removed because you know we didnt want to pay for it twice. in which we discussed with the builder at prestart.
the Builder has just come back to us (we are starting site works any day) and said there must be some confusion as their fee only covers the cost to run a cable and the db board rental and connection and NO trenching.
Is it just me or not, as my understanding of "builder to complete power and telecommunications run in lieu of by owner. meterbox on pole existing to site" was the complete installation...?
How did your build work in that respect. is 3k excessive for what they have allowed for seeing as they are no longer digging the trench and we are going to have to do it now and pay more.