Land situation...
Oct 2014 - Bought land at Wollert (supposed to be titled in March 2015)
Jan 2015 - Title pushed to June due to some drainage issue (pending council approval)
Mar 2015 - Title delay till Oct/Nov again
Oct 2015 - Delayed again !
Dec 2015 - Started to look for another location (got back the Wollert land 10% deposit)
Jan 2016 - Found a small corner block (titled) in Doreen
Mar 2016 - Paid and land registered..
Apr 2016 - Land settlement
Sep 2016 - Plan finalized
Nov 2016 - Building permit approval !
Dec/Jan - HOLIDAY
Feb 2017 - Slab poured
Builder (Clearview) especially the sales guy - MD, very accomodating with all the delay and changes on the land issue, but since it's been 2 years since i 1st signed with them, prices and selections changed, which is not great, but i managed to keep some of the upgrades, only issue i have with Clearview, is the admin lady ! But i wont go into detail, just want to move forward, and since now the build has started, the site supervisor, T (havent met him yet) 'sounds' good to me, as i've appointed building inspector, and it will be troublesome for him to let them know his schedule..
It's a small corner lot with side garage, only about 16sq (excluding the garage) so hopefully it wont take long for the build