3. Settlement ---------------------------------------09/02/2018 - Delayed Settelment ( suppose to be Aug 2017)
Ansa Homes #
.1. Kick Start my Home ----------------------------------17/07/2017
2. Formal Plan Fees-------------------------------------- 02/09/2017
3. Preliminary Works Agreement ----------------------29/09/2017
4. 10 % Fee PWA Bal ------------------------------------13/10/2017
Appointments #
1. Kitchen Appointment --------------------------- 20/11/2017
2. Colour Selections ------------------------------- 28/11/2017
3.Genneral Stairs -----------------------------------28/11/2017
4.Beaumont Tiles -----------------------------------06/12/2017
5. Electrical -Runnymade------------------------- 06/02/2018
1st Variation recevied ------------------------------29/03/2018
Update # 22/04/2018
Final Validation Tender Signed # 18/04/2018
HIA contract received-----------------------------23/04/2018
HIA Contract returned ---------------------------24/04/2018
CDC approved plan received-------------------24/04/2018
Approval #
1. Design Assesment approval By Land developer - 13/03/2018
2. Home Building Compensation Fund issued - 20/04/2018
3. Bank Conditional Approval # 09/05/2018 ( Note # Don't go with NAB way too slow)
4. Bank Unconditional Approval # 18/05/2018 ( 4 times the Quotation provided and uploaded to their system)
Construction Phase # * Aprox Date
Our project manager exceptionally good with his project management skills. Very helpful and honest with clients. He noticed an issue with window & roof ridge, notified me immediately and action plan to rectify the issue.
I really appreciate his afford to deliver our dream home quicker.
1. Site Preparation - 24/04/2018
2. Slab Pour - 09/05/2018
3. Frame - 18/05/2018
4. Brick Work - 16/06/2018 ( ***Rain Causing delays )
5. Brickwork Completed - 01/07/2018
6. Roof - Gutter - 02/07/2018
7. Internal Plumbing - 15/07/2018
8. Cladding, Electrical - 26/07/2018
9. Zip rock board - 03/08/2018
10. Stairs Installed - 03/08/2018
11. Kitched benchtops , cupboard installed 10/08/2018
12. Dooors, Paint 18/08/2018
13. Batroom tiles 22/08/2018
13 Garage Door ,More paint work , electrical work 03/09/2018
14. Benchtop stone Benchtop , cleaning 08/09/2018
15. PCI walkthrough - 12/09/2018
16. Final Handover - 09/10/2018
Like ⋅ Add a comment ⋅ Pin to Ideaboard ⋅
Like ⋅ Add a comment ⋅ Pin to Ideaboard ⋅
Like ⋅ Add a comment ⋅ Pin to Ideaboard ⋅
Like ⋅ Add a comment ⋅ Pin to Ideaboard ⋅
Like ⋅ Add a comment ⋅ Pin to Ideaboard ⋅
Like ⋅ Add a comment ⋅ Pin to Ideaboard ⋅
Like ⋅ Add a comment ⋅ Pin to Ideaboard ⋅
Blackbutt ( Austral bricks)Like ⋅ Add a comment ⋅ Pin to Ideaboard ⋅
Like ⋅ Add a comment ⋅ Pin to Ideaboard ⋅
Like ⋅ Add a comment ⋅ Pin to Ideaboard ⋅
Like ⋅ Add a comment ⋅ Pin to Ideaboard ⋅
Roof tilesClassic Yeoman Shingle NickelLike ⋅ Add a comment ⋅ Pin to Ideaboard ⋅
Like ⋅ Add a comment ⋅ Pin to Ideaboard ⋅