Ansa Homes | Hunter 30 | Build Time Line | HillCroft - NSW

Page 1 of 1
Landcom #

  • 1. Initial Land Deposit -------------------------------13/05/2017 -Landcom
  • 2. Land Deposit 5% --------------------------------27/06/2017 - Landcom
    3. Settlement ---------------------------------------09/02/2018 - Delayed Settelment ( suppose to be Aug 2017)



    Ansa Homes #
    .1. Kick Start my Home ----------------------------------17/07/2017
    2. Formal Plan Fees-------------------------------------- 02/09/2017
    3. Preliminary Works Agreement ----------------------29/09/2017
    4. 10 % Fee PWA Bal ------------------------------------13/10/2017



    Appointments #
    1. Kitchen Appointment --------------------------- 20/11/2017
    2. Colour Selections ------------------------------- 28/11/2017
    3.Genneral Stairs -----------------------------------28/11/2017
    4.Beaumont Tiles -----------------------------------06/12/2017
    5. Electrical -Runnymade------------------------- 06/02/2018

    1st Variation recevied ------------------------------29/03/2018



    Update # 22/04/2018

    Final Validation Tender Signed # 18/04/2018
    HIA contract received-----------------------------23/04/2018
    HIA Contract returned ---------------------------24/04/2018
    CDC approved plan received-------------------24/04/2018



    Approval #

    1. Design Assesment approval By Land developer - 13/03/2018

    2. Home Building Compensation Fund issued - 20/04/2018
    3. Bank Conditional Approval # 09/05/2018 ( Note # Don't go with NAB way too slow)
    4. Bank Unconditional Approval # 18/05/2018 ( 4 times the Quotation provided and uploaded to their system)





    Construction Phase # * Aprox Date


    Our project manager exceptionally good with his project management skills. Very helpful and honest with clients. He noticed an issue with window & roof ridge, notified me immediately and action plan to rectify the issue.

    I really appreciate his afford to deliver our dream home quicker.






    1. Site Preparation - 24/04/2018
    2. Slab Pour - 09/05/2018
    3. Frame - 18/05/2018

    4. Brick Work - 16/06/2018 ( ***Rain Causing delays )
    5. Brickwork Completed - 01/07/2018
    6. Roof - Gutter - 02/07/2018
    7. Internal Plumbing - 15/07/2018
    8. Cladding, Electrical - 26/07/2018
    9. Zip rock board - 03/08/2018

    10. Stairs Installed - 03/08/2018
    11. Kitched benchtops , cupboard installed 10/08/2018
    12. Dooors, Paint 18/08/2018
    13. Batroom tiles 22/08/2018
    13 Garage Door ,More paint work , electrical work 03/09/2018
    14. Benchtop stone Benchtop , cleaning 08/09/2018
    15. PCI walkthrough - 12/09/2018
    16. Final Handover - 09/10/2018





































    Hi, its coming along quite quickly.

    Im.looking at them at the moment and seem to have some good standard inclusions. Did you upgrade much?
    My biggest worry is the stair upgrade.

    Thanks
    Matt
    Related
    29/10/2023
    2
    Sewer line minimum depth in NSW

    Building A New House

    Hi, only for walking. It is a narrow 1.5m paved area next to house.

    21/10/2023
    0
    anyone build on zero lot line more than 11 meters? Urgent.

    Building A New House

    I am building in claymore NSW and this is shown in the building envelope plan. …

    2/05/2023
    4
    gas line re-purposed to water main?