Metricon provisional site costs
Page 1 of 1
We were told at our contract signing that the provisional costs can be lower and you get a refund of the difference but can't be any higher that what is put aside ? Anyone know more about this
You will need to do your own research and homework, ie geotech report, type footings, engineering upgrades, costs, etc,etc
See PROVISIONAL SUMS
For those that don't have HIA or MBA Contracts
"A provisional sum is an allowance (or best guess), usually estimated by a cost consultant, that is inserted into tender documents for a specific element of the works that is not yet defined in enough detail for tenderers to accurately price." Google
Slab & Formwork costs discussed here hth
"A provisional sum is an allowance (or best guess), usually estimated by a cost consultant, that is inserted into tender documents for a specific element of the works that is not yet defined in enough detail for tenderers to accurately price." Google
Slab & Formwork costs discussed here hth
Related
17/04/2024
1
Henley should give you some indication of site costs. Too many variable to give you any reasonable accuracy
13/12/2023
0
Hi, First of all, thank you to this community for sharing your thoughts and opinions. We are in early days of our pre-contract stage for Metricon Doulton and we are…