Browse Forums Building A New House Re: Building with MOMU at Brightwood (Baldivis) 62Apr 05, 2018 9:07 pm Imightbedave I’m a bit late to the party on this thread, but welcome to Brightwood! Your house design looks awesome. Thanks imightbedave. The family can't wait to move in. Re: Building with MOMU at Brightwood (Baldivis) 63Apr 05, 2018 9:10 pm So all the internal plaster has finished, and the all the doors have been delivered. We have been told that lock up should Monday at the latest. Master and Retreat. Hoping the SS will let me get in to seal the plaster once it dries out, anyone else get to do this? Like ⋅ Add a comment ⋅ Pin to Ideaboard ⋅ Like ⋅ Add a comment ⋅ Pin to Ideaboard ⋅ Re: Building with MOMU at Brightwood (Baldivis) 64Apr 05, 2018 9:39 pm Everything’s moving so quickly for you! Our SS gave us the option to seal it before lock up we apparently have a two day window to get it done. Maybe ask your SS if you can contact them direct or your CL? Re: Building with MOMU at Brightwood (Baldivis) 65Apr 05, 2018 11:30 pm We are painting our current house and mentioned to the Solver consultant that we are trying out a new colour for our new build. The consultant advised us to wait three months after white set to apply sealer and then wait a minimum of three days before starting to paint. Re: Building with MOMU at Brightwood (Baldivis) 66Apr 08, 2018 5:10 pm Choosy We are painting our current house and mentioned to the Solver consultant that we are trying out a new colour for our new build. The consultant advised us to wait three months after white set to apply sealer and then wait a minimum of three days before starting to paint. Thanks Choosy. So sealer once you get your keys sounds about right then. Hadn't heard of leaving it three days after sealer application. I wonder if the paint consultants are a little over conservative? Re: Building with MOMU at Brightwood (Baldivis) 67Apr 08, 2018 6:21 pm Mathew_Nikki Choosy We are painting our current house and mentioned to the Solver consultant that we are trying out a new colour for our new build. The consultant advised us to wait three months after white set to apply sealer and then wait a minimum of three days before starting to paint. Thanks Choosy. So sealer once you get your keys sounds about right then. Hadn't heard of leaving it three days after sealer application. I wonder if the paint consultants are a little over conservative? It was suggested to leave it a week to "harden" if you can. Having previously made the mistake of hanging pictures on walls the next day many years ago I have to agree 100%. Re: Building with MOMU at Brightwood (Baldivis) 68Apr 12, 2018 9:31 pm So we are locked out! I used to drop in every day, but seems like there is no point given that i can't get in Like ⋅ Add a comment ⋅ Pin to Ideaboard ⋅ Tiles have arrived, bath and laundry tub in. Like ⋅ Add a comment ⋅ Pin to Ideaboard ⋅ out tile selection; Like ⋅ Add a comment ⋅ Pin to Ideaboard ⋅ Like ⋅ Add a comment ⋅ Pin to Ideaboard ⋅ Like ⋅ Add a comment ⋅ Pin to Ideaboard ⋅ Re: Building with MOMU at Brightwood (Baldivis) 69Apr 12, 2018 10:38 pm I hate when you can’t get in I’m pretty sure we have that last white tile too my new build thread- Ben Trager https://forum.homeone.com.au/viewtopic.php?f=31&t=89826 my switch build thread (2011) https://forum.homeone.com.au/viewtopic.php?f=31&t=36569 Re: Building with MOMU at Brightwood (Baldivis) 70Apr 14, 2018 9:53 pm Yeah I waited as long as possible to seal the walls. I wouldn't worry about it until after handover. Are you doing your own flooring, or is that part of the build? Find my build thread here: https://forum.homeone.com.au/viewtopic.php?t=88694&f=31&p=1729530#p1729530 Re: Building with MOMU at Brightwood (Baldivis) 71Apr 14, 2018 11:01 pm Garage grano in. Painters is currently doing the door frames and doors. Still waiting on the front weatherboard to go in. The carpenter wasn't happy that the boards had been sitting there for 2 months and been messed up a bit, so got the SS to order new ones. Just_a_draftee - flooring is included, so just means messing around with covering the floor when we paint. Like ⋅ Add a comment ⋅ Pin to Ideaboard ⋅ early morning drive by Like ⋅ Add a comment ⋅ Pin to Ideaboard ⋅ Re: Building with MOMU at Brightwood (Baldivis) 72Apr 15, 2018 1:04 am Looks good! Baffles me why they'd order the boards so far in advance and not install them ... Find my build thread here: https://forum.homeone.com.au/viewtopic.php?t=88694&f=31&p=1729530#p1729530 Re: Building with MOMU at Brightwood (Baldivis) 73Apr 29, 2018 12:56 pm Been a little while since our last post. Been way too busy with a new position at work. Things have been going well, tiling is happening now, and should be finished this week. Should have PCI around 15th June. Like ⋅ Add a comment ⋅ Pin to Ideaboard ⋅ Like ⋅ Add a comment ⋅ Pin to Ideaboard ⋅ Like ⋅ Add a comment ⋅ Pin to Ideaboard ⋅ Re: Building with MOMU at Brightwood (Baldivis) 74May 26, 2018 10:49 pm how's your build coming along guys? Thanks for your reply. I will just wait and see I guess. Trying to get some more information from our builder. 9 30233 go upvc window frames ensure insulation under colorbond. not just sarking, lighter color roof also not sure if you have seen this viewtopic.php?t=5823 last couple of pages… 4 110226 |