Hi all
Long time viewer of this forum which has greatly assisted myself with research. I am building a variation of the alkira 12.5 with S/ummit. Timeline so far:
* 31/08/17 Settled on block of land
* Mid August signed PPA with Summit
* Contract signed end Sept 2017
* Interior Design Consult 25th Oct
* Tile Selection 26th Oct
* Pre-Start 8th Nov
* 13th November signed off on pre-start variation & developer approval received
* 22 Nov Final documentation received, resubmitted to correct errors
* Energy approval received 23/11/17
* 30th Nov final documentation approved
* 30th Nov progressed to scheduling
* 2/12/17 visited block and found a water meter in place!
* 4/12/17 Finance Approved
* 5/12/17 Signed off final plans with engineering detail
*19/12/17 Building Permit approved *** added 20/12/17
* 11/1/18 Siteworks
* 18/1/18 Footings done
*19/1/18 Slab poured
* 29 or 30th Jan Soakwells installed
*31/1/18 Drains done
*2/2/18 Site cleared/cleaned
*5/2/18 bricks delivered
*6/2/18 Site shed, toilet & frames delivered
Just waiting on private certification (which is due back tomorrow) and building permit. My fingers are crossed i will see a slab on my patch of sand before xmas. This has been my goal since October and would make the tedious & stressful process of paperwork & dealing with banks well worth it! My salesman is fairly confident this will happen.