Timeline;
Land development was completed – DEC 2016
Building Contract signed- DEC 2016
Land Registered – JUN 2017
Building plans finalised – OCT 2017
Council Approval submitted – OCT 2017
Council Approval completed – Late OCT 2017
Finance Approved – 3rd NOV 2017
Slab went down – 9th NOV 2017
Frames started going up – 13th NOV 2017
Frames completed - 24th NOV 2017
Plumbing and Gas pipes completed - 29th NOV 2017
Guttering and roof started - 29th NOV 2017
Guttering and roof completed - 30th NOV 2017
Airconditioning installed - 5th DEC 2017
Electrical rough-in - 12th - 13th DEC 2017
Insulation installed - 15th DEC 2017
Bricks started - 20th DEC 2017
Bricks completed - 5th JAN 2018
Gyprock sheeted - 8th JAN 2018
Plastering started - 9th JAN 2018
Plastering completed - 12th JAN 2018
Eavs started - 15th JAN 2018
Eavs completed - 18th JAN 2018
Internal carpentry (Doors, architrays, wardrobes etc) started - 19th JAN 2018
Kitchen, Laundry and Study installed and finished - 24th JAN 2018
Internal carpentry completed - 26th JAN 2018
Tiles started - 30th JAN 2018
Tiles completed - 5th FEB 2018
Stone benches installed - 9th FEB 2018
Painting started - 13th FEB 2018
Painting finished - 23rd FEB 2018
Garage door Installed - 23rd FEB 2018
Final Electrical & Plumbing started - 26th FEB 2018
Final Electrical & Plumbing completed - 3rd MAR 2018
Driveway, step and pad boxed up - 28th FEB 2018
Final Fitout started - 3rd MAR 2018
Driveway poured - 5th MAR 2018
Final fitout completed - 9th MAR 2018
Site scrape, level and clean-up - 9th MAR 2018
PCI Inspection - 12th MAR 2018
Expected Keys - 16th MAR 2018
Ill keep updating with photos and time frames for anybody interest during each process of the build.