We are building with Oracle and in the contract it states "building works must be reach the practical completion no more than 140 working days after the building period commences" this was the 17th October 17.
I have emailed Oracle and I am not getting anywhere, last email was 5 days ago and still have had no reply and that was to the Operations Manager!!
What I can see that is still needed to be finished is the following:
Carpets to be laid in bedrooms
2 x Shower Screens
2 x Mirrors above vanities
Kitchen appliances
Painting touch ups
Robe doors to be fitted
Landscaping and fencing
Letterbox
The house to be cleaned
This all could be done if they were organised but still have no idea if it will be ready for Xmas.
My question is what do I do next as Oracle don't seem to come back to me and it's getting ridiculous with how long it's been going on for. Was first told it would be built by March 17, then finished for August 17 it's now November and they will not confirm a date.
Appreciate any advice