Browse Forums Building A New House Re: Individual Design - New Choice Homes 319Jun 20, 2018 10:15 am PCI booked for the 28.6.18, 31 weeks since slab down and about 12 weeks since lockout. I fine tuned our landscaping plan and submitted it to Reece Plumbing last night, should have our irrigation plan back in a week. Lucky that I had dabbled with Sketchup before as hubby failed to mention that I had to do the plan online..... it is not perfect but not bad for a evening effort. Like ⋅ Add a comment ⋅ Pin to Ideaboard ⋅ Hi there! Putting the feelers out there for those who have (or almost) built with Arli homes! Interested in your experiences who've built from their stock home designs… 0 1368 Ask for references and speak to them. If they are defensive or try to avoid the request, walk. 1 47293 I would never build with Fowler homes. I built with them in 2021 and till date maintenance issues are pending. All their existing trades and businesses don't work with… 14 73521 |