TIMELINE

ADMINISTRATION STAGE
Contract signed: 08.08.2017
Cosham finishes session: 09.08.2017
YHC electrical session: 15.08.2017
Covenant approval: 29.08.2017
Authority approval: 12.09.2017
PCV complete: 13.09.2017
Final drawings complete: 25.09.2017
Handover to construction: 13.10.2017

CONSTRUCTION STAGE
Site cut: 31.10.2017
Site plumbing & electrical: 07.11.2017
Slab formwork: 08.11.2017
Slab pour: 09.11.2017
Frame commenced: 22.11.2017
Frame completed: 24.11.2017
Roof commenced: 30.11.2017
Electrical rough in 12.12.2017
Plumbing rough in 13.12.2017
Aircon rough in 14.12.2017
Roof complete 15.12.2017
Windows installed 22.12.2017
Brickwork commenced 16.01.2018
Brickwork completed 20.01.2018
Plastering commenced 30.01.2018
Rendering completed 06.02.2018
Cladding commenced 09.02.2018
Plastering completed 12.02.2018
Cladding completed 12.02.2018
LOCKUP 17.02.2018
Stairs installed 19.02.2018
Carpentry fix (doors, skirtings, architraves) installed 23.02.2018
Joinery installed 03.03.2018
Tiling commenced 03.03.2018
Painting commenced 17.03.2018
Stone tops installed 20.03.2018
Internal paint completed 22.03.2018
Roof plumbing fix 23.03.2018
Garage doors 05.04.2018
Plumbing fix 06.04.2018
Electrical fix 06.04.2018
Shower screens, Wardrobe fitout, Glass splashbacks 23.04.2018
Driveway installed 01.05.2018
Pre-handover inspection 09.05.2018
HANDOVER 14.05.2018
30.10.2017
07.11.2017
Good afternoon SDP,

Your land is so flat !!!!!!! How big was the land ??
ERIC Y
Good afternoon SDP,

Your land is so flat !!!!!!! How big was the land ??

500 m2, yes no retaining wall required
08.11.2017
Nice!! Where in QLD are you building?
akashsethi10
Nice!! Where in QLD are you building?

Haha pretty sure that is your house in the background
It certainly is. I knew it looked familiar.
09.11.2017



22.11.2017
25.11.2017
02.12.2017
Great progress! Looking to hope on the Plantation band wagon soon myself =D

Let me get this right, you went from signing to construction in 2 months????
15.12.2017

22.12.2017

Coming along nicely, the Seville was the way we were going to go if we didn't go custom! It looks great and can't wait to see more pics
16.01.2018
Wooo Bricks going on , what's your width of your land ?
ERIC Y
Wooo Bricks going on , what's your width of your land ?

12.5m
Related
5/09/2023
0
QLD Owner Builder Legislation.

General Discussion

Hi all. Anyone know when the $11,000 limit was set in legislation for renovations in QLD? Ive been renovating for 5 years now and this was the limit back then. As we know,…

15/02/2024
0
QLD - Builder finished without notifying Building Certifier

General Discussion

Hi, I contracted a Builder to do a Garage to Bedroom + ensuite conversion (Class 1a), the Builder engaged the Certifier and Engineer and received BDA from the Certifier…

5/03/2024
3
Looking for the perfect design - 2 storey in Qld

Building A New House

We used a smaller qld builder who went bankrupt about 12 months after completion of ours. It was a shame as they were good and relatively cheap and I would have used…

You are here
Building ForumBuilding A New House
Home
Pros
Forum