Browse Forums Building A New House Re: Ausbuild Finlay 36 @ Kinross Road Thornlands 23May 21, 2018 7:53 am Land deposit: 17 Nov 16 Build contract: 17 Apr 17 Land settled: 16 June 17 BA: 23 June Slab: 3 Aug Frame: 21 Aug Enclosed: 10 Oct Fixing: 6 Nov PCI: 14 Dec Settlement: 21 Dec 17 https://forum.homeone.com.au/viewtopic.php?f=31&t=88597 https://forum.homeone.com.au/viewtopic.php?f=31&t=88597 Re: Ausbuild Finlay 36 @ Kinross Road Thornlands 25May 22, 2018 7:01 am Land deposit: 17 Nov 16 Build contract: 17 Apr 17 Land settled: 16 June 17 BA: 23 June Slab: 3 Aug Frame: 21 Aug Enclosed: 10 Oct Fixing: 6 Nov PCI: 14 Dec Settlement: 21 Dec 17 https://forum.homeone.com.au/viewtopic.php?f=31&t=88597 https://forum.homeone.com.au/viewtopic.php?f=31&t=88597 Re: Ausbuild Finlay 36 @ Kinross Road Thornlands 26May 22, 2018 7:02 am Land deposit: 17 Nov 16 Build contract: 17 Apr 17 Land settled: 16 June 17 BA: 23 June Slab: 3 Aug Frame: 21 Aug Enclosed: 10 Oct Fixing: 6 Nov PCI: 14 Dec Settlement: 21 Dec 17 https://forum.homeone.com.au/viewtopic.php?f=31&t=88597 https://forum.homeone.com.au/viewtopic.php?f=31&t=88597 Re: Ausbuild Finlay 36 @ Thornlands - Lock up! 35Jul 27, 2018 10:58 pm Thanks mj-mac4 and Valandra. Few hicups along the way but that is to be expected with a project builder. Site supervisor is terrific and has made a huge difference. Although we are on the 2nd SS and 3rd Customer Services Officer. I blame the wife for being too demanding! Unfortunately there is no comms page on Facebook or this site specific for Ausbuild. Although on this site there are a few threads from builds that have now completed and I think there are three currently underway including this one. All the best with your builds. Exciting and stressful at the same time! Sort of like Christmas lunch at the in-laws Cheers, Paul Re: Ausbuild Finlay 36 @ Thornlands - Lock up! 36Aug 07, 2018 7:29 am Garage door is on and tiling commenced this week. Garage door is finally onLike ⋅ Add a comment ⋅ Pin to Ideaboard ⋅ Ensuite - unfortunately basins are wrong and are to be replaced.Like ⋅ Add a comment ⋅ Pin to Ideaboard ⋅ Main shower. There are two rain showers from ceiling and no doors.Like ⋅ Add a comment ⋅ Pin to Ideaboard ⋅ Shower is behind this wall. Freestanding bath will be in front.Like ⋅ Add a comment ⋅ Pin to Ideaboard ⋅ Kitchen looking to butlers pantry. Front door is on right of pictureLike ⋅ Add a comment ⋅ Pin to Ideaboard ⋅ Re: Ausbuild Finlay 36 @ Thornlands - Lock up! 38Aug 08, 2018 10:12 pm mj-mac4 Looks great!! I love the garage door!! Thanks mj-mac4...of course it was an upgrade! Everything that is nice is an upgrade. During our admin stage we learnt that you need big pockets and little surprises keep happening just when you thought it was all covered I have been silently following your build and glad to see the niche grout is being fixed. White will much better. Our build started around the same time as yours but we are still around 13 weeks away from hand over - maybe more if the tiler doesn't get a start. Was supposed to be Monday but still has not commenced Good luck with your remaining time and why oh why would you think of doing it a second time so soon! We have sworn this is our last. Re: Ausbuild Finlay 36 @ Thornlands - Lock up! 39Aug 09, 2018 11:29 am pbwhi0 mj-mac4 Looks great!! I love the garage door!! Thanks mj-mac4...of course it was an upgrade! Everything that is nice is an upgrade. During our admin stage we learnt that you need big pockets and little surprises keep happening just when you thought it was all covered I have been silently following your build and glad to see the niche grout is being fixed. White will much better. Our build started around the same time as yours but we are still around 13 weeks away from hand over - maybe more if the tiler doesn't get a start. Was supposed to be Monday but still has not commenced Good luck with your remaining time and why oh why would you think of doing it a second time so soon! We have sworn this is our last. Lol everything is an upgrade 😂😂 even through our construction they are the ting to sting us for more money. Looking forward to seeing your tiles soon!! 🎉🎉 Re: Ausbuild Finlay 36 @ Thornlands - Tiling commenced! 40Aug 19, 2018 8:21 pm Some photos of the tiling... Like ⋅ Add a comment ⋅ Pin to Ideaboard ⋅ Floor plan of main bedroom and ensuite/WIR Like ⋅ Add a comment ⋅ Pin to Ideaboard ⋅ Main ensuite - toilet top right, left wall is feature dark tile with free standing oval bath. Pipe in floor is floor mount bath spout. Tap is on wall just under niche on left side (out of camera shot). Like ⋅ Add a comment ⋅ Pin to Ideaboard ⋅ Main ensuite shower (3.8m long) with 2 x ceiling mount rain showers. Wall on right is backside of bath wall and will be feature dark tile. All other walls will be light tile from floor. Like ⋅ Add a comment ⋅ Pin to Ideaboard ⋅ Main ensuite - still waiting for vanity basins and bench to be replaced. Should have been oval basins that sit on top. Like ⋅ Add a comment ⋅ Pin to Ideaboard ⋅ Second bathroom - Jack and Jill between bed 2 & 3. Like ⋅ Add a comment ⋅ Pin to Ideaboard ⋅ Third bathroom - Jack and Jill between bed 4 & 5. This week the walls of bathrooms should be tiled. Painting prep is also to commence. Can you give advice on how to get missing certificates needed for a form 21? Our bank requires us to provide one but we are missing 4 building certificates from our first… 3 57057 yes it does, you've just not understood it. theres a difference. 4 2780 Your house should come in "as new" condition. It should be clean, and without stains 1 2857 |