o0_zoe_00
Only just... The contract end date is at the end of this month although they did claim quite a number of weather and trade delays very early on. Some were contested so im waiting to hear back about exactly when the record liquidated damages commencing but by my calculations its early next month.
Inside our house is essentially complete and its now been over a month of waiting for a resolution on how and when the bricks will be rectified. We've recently been told the delay is sourcing a re-pointer...
Inside our house is essentially complete and its now been over a month of waiting for a resolution on how and when the bricks will be rectified. We've recently been told the delay is sourcing a re-pointer...
We have six weeks left, so far no claims for extensions. We are still tiling , although data and electrical fit offs have been done (need rectification still). Outside we need paint, concrete, gas line, site clean and garage door. Last word they were still quite sure they would make end of contract, we are highly doubtful, by Christmas is our aim (isn't everyones!).