Colour Selections - Page 6
Electrical Plans - Page 8
Build Start - Page 12
Hey all!
Myself and my partner (Nicole) have taken the jump to build our first home and we have decided to go with the coral noosa 23 design in Ormeau Hills. Tomorrow we are going to put down our holding deposit on the land and we are going to have our appointment to get our building contracts under way. We are still waiting for our conditional finance approval to come through but our broker is very confident we will get the approval we need!
Cannot wait to get everything started and the journey ahead

Noosa 23 Designer Inclusions
Raised Ceilings ($1750)
Upgraded bathrooms to Elegance ($3999)
Kitchen Upgrades to elegance and appliance upgrades ($1999)
Full house tiling and carpet ($2999)
Street Appeal Upgrade ($499)
Removed builder supplied driveway (-$7500)
Removed builder fencing (-$2500)
Remove builder turf supplies (-$1300)
Remove builder letter box (-$250)
Remove builder supplied alfresco slab (-$1820)
Modify front room to be study.
Extend media room to provide more space.
Remove Builder supplied WIR fit out to do our own Ikea PAX.
Added full glass door to Laundry,
Added sliding door to dining room area.
We are also going to be doing only the items that are extremely difficult/expensive to do post handover in our electrical appointment, so things like lights on the front pillars, internal powerpoints and 413QC connections in the roof for us to do after handover and we will supply all pendants and fans and pay the sparky onsite.Here are our plans and our land!!!
Like ⋅ Add a comment ⋅ Pin to Ideaboard ⋅
Like ⋅ Add a comment ⋅ Pin to Ideaboard ⋅
Building timeline:
Start Date - 3rd November
Retaining wall - 7th/8th November
Site Scrape - 11th November
Piers - 14th November
Plumbing - 16th November
Slab Prep - 20th November
Slab Pour - 21st November
Back Blade - 22nd November
Temp Fencing - 23rd November
Frame Delivery - 27th November
Frame Start - 28th November
Frame Completion - 1st December
Gutters and Fascia - 2nd December
Gutters and Fascia Completed - 4th December.
Roof Start - 6th December
Roof pointing - 11th December
House wrap, doors and windows - 11th December
Rough ins - 12th December
Bricks start - 14th December
Bricks finished - 27th December
Eaves start - 15th January
Eaves Complete - 16th January
Architraves, Skirting and internal doors - 16th January