Spoke with new SS today. Painting and electrical fit off have been completed.
All cabinetry and tiles have been delivered, kitchen was to be installed today/tomorrow with tilers to start once kitchen and vanities are in towards the end of this week.
Final site clean has been booked for 15th Feb, timber floorboards have been booked for 19th Feb and Carpet 21st Feb....then we're pretty much done!!! Garage door and driveway to be done after that.
Getting so close now, feel like I still have a million things to buy and organise before we move in though. 4-5 weeks to go! Having a walk through this Friday so will hopefully be able to post some pics then.