Henley Electra 2017/2018 build
Page 3 of 4
It's all coming together beautifully!!
Frame stage completed ✔️
Roofing completed ✔️
Plumbing rough in completed ✔️
Everything Darbecca picked up in inspection was all fixed by Henley without any problems
Check out the videos below to see the house in more detail
[youtube]https://youtu.be/jMRGOUVm0N4[/youtube]
[youtube]https://youtu.be/ggCH3tShcFc[/youtube]
[youtube]https://youtu.be/muQhKK96P1Q[/youtube]
Week 7
It's all coming together beautifully!!
Frame stage completed ✔️
Roofing completed ✔️
Plumbing rough in completed ✔️
Everything Darbecca picked up in inspection was all fixed by Henley without any problems
Check out the videos below to see the house in more detail
[youtube]https://youtu.be/jMRGOUVm0N4[/youtube]
[youtube]https://youtu.be/ggCH3tShcFc[/youtube]
[youtube]https://youtu.be/muQhKK96P1Q[/youtube]
It's all coming together beautifully!!
Frame stage completed ✔️
Roofing completed ✔️
Plumbing rough in completed ✔️
Everything Darbecca picked up in inspection was all fixed by Henley without any problems
Check out the videos below to see the house in more detail
[youtube]https://youtu.be/jMRGOUVm0N4[/youtube]
[youtube]https://youtu.be/ggCH3tShcFc[/youtube]
[youtube]https://youtu.be/muQhKK96P1Q[/youtube]
Thanks earcangel for sharing the pics and video. After looking at that,I am feeling more confident on my decision to go with Electra
Looking great! Good to see it’s progressing so well for you. I hope the momentum continues!
Week 7
It's all coming together beautifully!!
Frame stage completed ✔️
Roofing completed ✔️
Plumbing rough in completed ✔️
Everything Darbecca picked up in inspection was all fixed by Henley without any problems
Check out the videos below to see the house in more detail
[youtube]https://youtu.be/jMRGOUVm0N4[/youtube]
[youtube]https://youtu.be/ggCH3tShcFc[/youtube]
[youtube]https://youtu.be/muQhKK96P1Q[/youtube]
It's all coming together beautifully!!
Frame stage completed ✔️
Roofing completed ✔️
Plumbing rough in completed ✔️
Everything Darbecca picked up in inspection was all fixed by Henley without any problems
Check out the videos below to see the house in more detail
[youtube]https://youtu.be/jMRGOUVm0N4[/youtube]
[youtube]https://youtu.be/ggCH3tShcFc[/youtube]
[youtube]https://youtu.be/muQhKK96P1Q[/youtube]
Thanks earcangel for sharing the pics and video. After looking at that,I am feeling more confident on my decision to go with Electra
Hi dreamhomz,
To be honest, we were really worried because we hadn't really seen this house in great detail, but as it is coming along it is longing more and more amazing and we are so happy with the changes we are seeing. I feel great peace in deciding to build the Electra.
With regards to the Theatre Room size, I think it is a decent size but if it was a little wider it would have been awesome. It all depends on how chunky your recliners are. We are putting a 4 seater with a chaise but ours is not very chunky. I would be so happy for you to check out our place but I am not sure if Henley will let you through.
Have they started your house as yet?
Looking great! Good to see it’s progressing so well for you. I hope the momentum continues!
It has been great so far justmia, they have done a lot so far in 7 weeks considering they had to stop and we lost almost 2 weeks because they had to fix a few things that our personal inspectors picked up at Frame Stage Inspection. Hoping for a productive season on the build.
Your posts are awesome and it gives a good insight of electra as there are no display homes which is unfortunate. I have decided to go with Henley for the electra. Its a beautiful design. I have all the upgrades I require and planning to visit henley tomorrow to get a quote. The 40mm caesar benchtop which you have quoted, is that a category 1 or x?
Yay! So we had our Colour Selection today with Henley. Very professional! We had Isabella as our Colour Consultant, she was amazing, so patient and lovely to deal with.
As mentioned previously, this is our 3rd time building with Henley. The Colour Selection process has improved significantly. Gone are the days when we were in a small room with minimal samples on display. Now they have a fantastic showroom which is set up so well with everything on display. They even provided us with lunch, hot and cold drinks (including my children). Really Impressed. Anyway let’s get back to my Colour Selection
EXTERIOR
KITCHEN
Other added items to Kitchen
BUTLER’S PANTRY
Other added items to Butler’s Pantry
ENSUITE
Other added items to Laundry
BATHROOM
W.C (TOILET)
POWDER ROOM
LAUNDRY
Other added items to Laundry
OTHER COLOUR SELECTION
Internal walls & Woodwork
Staircase
We have organised our flooring and window furnishings outside of Henley. This will be done after handover.
Tried to include as much as I can, hope this all helps
Next is Tender late July and Contract Signing end of August
As mentioned previously, this is our 3rd time building with Henley. The Colour Selection process has improved significantly. Gone are the days when we were in a small room with minimal samples on display. Now they have a fantastic showroom which is set up so well with everything on display. They even provided us with lunch, hot and cold drinks (including my children). Really Impressed. Anyway let’s get back to my Colour Selection
EXTERIOR
- Added ‘Grand Garage Pack’
- Added ‘Statement Entry Pack’
- Brick: Austral – Pepperwood (Category 4)
- Mortar: Off White (Rolled)
- Roof Tile Profile: Heritage
- Roof Tile Colour: Blackstone
- Gutter/Fascia/Downpipes/Meter Box: Monument
- Flashing: Dune
- Aluminium Windows Colour: Dune
- Garage Door Style: Slimline
- Garage Colour: Caoba
- Rear Roller Door Colour: Dune
- Front Door Size: 2400mm x 920mm
- Front Door Style: Corinthian MAD101 with Translucent Glass Panel
- Front Door Stain: Rich Chocolate
- Front Side Light: Clear
- Main Render Colour: Bogart
- Feature Render: Taupe Stone
KITCHEN
- Added ‘Entertainer’s Kitchen Pack’
- Rear Benchtop: 40mm CaesarStone Category 1 (with shadow line)
- Island Benchtop: 40mm CaesarStone Category 1 (with shadow line)
- CaesarStone Colour: Osprey
- Overhead Cupboards: Riven Parchment (with no handles)
- 2 x Wall Oven Towers: Natural – Parchment (with stainless steel handles)
- Base Cabinets: Natural – Parchment (with stainless steel handles)
- Glass Splashback: Scallopino
Other added items to Kitchen
- 900mm Technika Cooktop
- 900mm Smeg Concealed Rangehood
- 2 x 600mm Technika Ovens
- Double Undermount Sink & Multi-Function Tap Mixer
- 3 sets of Pot Drawers (rear bench under Cooktop)
BUTLER’S PANTRY
- Benchtop: 40mm CaesarStone Category 1
- CaesarStone Colour: Osprey
- Overhead Cupboards: Riven Parchment (with no handles)
- Base Cabinets: Natural – Parchment (with stainless steel handles)
- Glass Splashback: Scallopino
Other added items to Butler’s Pantry
- Round Sink and Gooseneck Tap
- 4 shelves for pantry items
ENSUITE
- Added ‘Ensuite Grandeur Pack’
- CaesarStone Benchtop: Osprey - 20mm CaesarStone Category 1 (with shadow line)
- 2 Vanity with 3 Draws: Riven – Licorice Linea (with handles)
- Wall Tile (Floor to Ceiling): Category 1 – Bone White (300x600 #MMLWK0101) with White Grouting (#200)
- Floor Tile: Category 3 – Cloud Mahogany (450x450 #1TIL0243) with Slate Grey (#211)
- Feature Tile (Wall and Hob of Bath): Category 3 – Cloud Mahogany (450x450 #1TIL0243) with Slate Grey (#211)
- Tapware: Rush Series
- Accessories Collection: Radii (Square)
- Toilet: Raymor Edge - Wall to Wall (upgrade)
- Basin: Seima - Rectangular Plati (upgrade)
Other added items to Laundry
- Cavity slider to Ensuite
BATHROOM
- Added ‘Bathroom Bliss Pack’
- CaesarStone Benchtop: Osprey - 20mm CaesarStone Category 1 (with shadow line)
- Single Vanity with 3 Draws: Riven – Licorice Linea (with handles)Wall Tile (Floor to Ceiling): Category 1 – Bone White (300x600 #MMLWK0101) with White Grouting (#200)
- Floor Tile: Category 3 – Cloud Mahogany (450x450 #1TIL0243) with Slate Grey (#211) Hazelnut (450x450 #1TIL0242) with Olive Grouting (#395)
- Feature Tile (Wall and Hob of Bath): Category 3 – Cloud Mahogany (450x450 #1TIL0243) with Slate Grey (#211)
- Tapware: Rush Series
- Accessories Collection: Radii (Square)
- Basin: Seima - Rectangular Plati (upgrade)
W.C (TOILET)
- Floor Tile: Category 3 – Cloud Mahogany (450x450 #1TIL0243) with Slate Grey (#211)
- Accessories Collection: Radii (Square)
- Toilet: Raymor Edge - Wall to Wall (upgrade)
POWDER ROOM
- CaesarStone Benchtop: Osprey - 20mm CaesarStone Category 1
- Laminate Skirt: Riven – Licorice Linea
- Floor Tile: Category 3 – Cloud Mahogany (450x450 #1TIL0243) with Slate Grey (#211)
- Feature Tile (above bench): Honed Light Coffee Stone (#1TIL0132) with White Grouting (#20)
- Tapware: Rush Series
- Accessories Collection: Radii (Square)
- Toilet: Raymor Edge - Wall to Wall (upgrade)
- Basin: Seima Plati Counter Top
LAUNDRY
- Added ‘Laundry Smarts Pack’
- Laminate Benchtop: Natural – Platinum Micro
- 3 Base Portrait Cabinets : Natural – Licorice Linea(with handles)
- Wall Tile (Floor to Ceiling): Category 1 – Gloss Ivory(TAKW10404) with Alabaster Grouting (#282)
- Floor Tile: Category 3 – Cloud Mahogany (450x450 #1TIL0243) with Slate Grey (#211)
- Tapware: Gooseneck Tap
- Basin: Stainless Steel Trough
Other added items to Laundry
- Cavity slider to WIL
- 900mm Broom Cupboard
OTHER COLOUR SELECTION
Internal walls & Woodwork
- Wall Paint (entire house): Whisper White
- Woodwork (Skirtings, Architraves & Internal Plush Door): Whisper White (Gloss)
Staircase
- Under Staircase Storage (moved to Entry Area)
- Handrail: Vic Ash with Rich Chocolate Stain
- Balusters: Stainless Steel
We have organised our flooring and window furnishings outside of Henley. This will be done after handover.
Tried to include as much as I can, hope this all helps
Next is Tender late July and Contract Signing end of August
Hi , Your post is awesome .. I am also finalizing to build Henley Aegan 45 , you mentioned in your post that you are doing your flooring from external vendor .. Can you share details of that vendor ?? . Trying to get quote externally to compare what henley is pricing me for . Thanks
so i have asked henley to do similar modifications and at this moment have flatly said no. i will be calling henley to see if i can get the ok from someone higher up. but thank you for the insight!
Any luck? I have been told that they cant upgrade to 40mm benchtop and butlers pantry upgrade as this is essence collection. Looks like marketing strategy to push people to move to the next level.
Hows your build progressing? Henley’s measurement for the living room is not correct which I came to know after receiving detailed drawings 😞
Is carpet choice cheaper than henley quote? Also is the evaporative cooling what Henley gives is good? Its a brivis p36 with 5 outlets for first floor only. I read in product reviews and the scope is 1.4/5
Hope your build is going well.
It's been a while since you posted your last update.Is everything good?
Our land is also getting close to entitlement and was curious to know how is yours going.
Thanks in advance.
Related
16/04/2024
1
Hi, If you give a set of criteria as to what means 'good' to you, it'll give others prompts to respond. We considered Henley early on but there were two factors that…
21/02/2024
7
Thank you so much everyone. This all makes a lot of sense. I guess when you talk to a builder who butters up everything to look very polished, you get to start believing…
25/05/2023
0
Hi We have finally decided to complete a KDR on our corner plot in NE Melbourne suburbs. Given its a corner plot approx. 400 sqm just a standard design may not fit the…