First home owner and first time builder here. Hoping to connect with other single storey Fowler Homes owners (seems to be a lack of us!) or people currently within Tranche 31 Stage 2 (registration in OCT/NOV 2017) at Oran Park; Lots 1130 - 1295. We might find our neighbours on this thread!
Building the Catalina 23 with the Allegra facade; Deluxe Package. I'll try and update costs of things in the post below.
Like ⋅ Add a comment ⋅ Pin to Ideaboard ⋅
Our current timeline with Fowler:
27 May 17 - Land secured
05 June 17 - Tender Presentation
22 June 17 - Plan and Tender Variation signed
03 August 17 - 1st Draft received
03 September 17 - TV 3 signed
19 September 17 - TV 4 signed
26 September 17 - Council Forms signed
28 September 17 - 2nd Amended Draft received and signed
19 October 17 - Land is registered
02 November 17 - Land settled
22 November 17 - Developer Approval for Oran Park Rebate accepted
27 November 17 - TV 5 & 6 signed
27 November 17 - Colours Appointment / Ultra Air (air con) / Appointment TV 7 signed
04 December 17 - Brindabella Kitchen Appointment / Abruzzo Tiling Appointment
06 December 17 - DA lodged to Camden Council
17 December 17 - TV 8 signed
07 January 18 - Clipsal Appointment
01 January 18 - TV 9 signed (Development Consent)
28 January 18 - Tiling signed / Kitchen signed
03 February 18 - Council strip tree replanted away from driveway
14 February 18 - TV 10 signed / Tiling floor wastes variation signed / Kitchen drainage variation signed
23 February 18 - TV 11 signed
27 February 18 - Construction Plans received
12 March 18 - Construction Plans signed
15 March 18 - HIA contract recieved
20 April 18 - HIA contract back with builder
15 May 18 - In Production
13 June 18 - Construction to commence
20 June 18 - Colours Doc 3 signed
29 June 18 - Piering & Draining done
06 July 18 - Slab poured
19 July 18 - Frames delivered
24 July 18 - Trusses delivered
30 July 18 - Plumbing
31 July 18 - Bricklaying
16 August 18 - Facia & gutter installed
17 August 18 - Roof tiles delivered
20 August 18 - Roof tiles installed
23 August 18 - Eaves installed
25 August 18 - Bricks cleaned
30 August 18 - Electrical rough-in & Gyprock delivered
07 September 18 - Gyprock complete. Doors Delivered
13 September 18 - Waterproofing
20 September 18 - Cabinetry installed
02 October 18 - Tiling started
17 October 18 - Skirting installed
18 October 18 - Notified of discontinued stone-top (Cygnus)
26 October 18 - Painting complete
31 October 18 - New stonetops installed
01 November 18 - Tapware installed
07 November 18 - 1st house clean done & Laundry/Alfresco steps complete & rubbish removed
09 November 18 - Kitchen splashback due to be completed (due to incorrect stock) & mirrors installed
19 November 18 - Carpet installed
20 November 18 - Door stain fixed
21 November 18 - 1st house walk through
22 November 18 - Driveway poured
26 November 18 - Painter in for touchups, gaps above windows fixed
27 November 18 - Inspection with certifier. IOC due end of week
30 November 18 - 2nd house walk through
01 December 18 - Painter in again
03 December 18 - Driveway sealed
08 December 18 - Alfresco Door replaced
14 December 18 - (estimated) Handover date
Looking forward to discussing your homes with you