Browse Forums Building A New House 1 Jan 30, 2017 2:41 pm Land Size : 12.5m X 30m = 375sqm
Building Marina Q2 Facade:Milton Total Area (Squares) : 22.3 sq Stage 1: Base Start Date: 15-Jan-2017 End Date: 27-Jan-2017 Pre-pour inspection completed Stage 2: Frame Start Date: 30-Jan-2017 Completed Date: 10-Feb-2017 Frame inspection completed Stage 3: Lock-up Start Date: 13-Jan-2017 In Progress... ETC 24-Feb-2017 Pre-Plaster inspection scheduled for 18-Feb-2017 Re: Building Marina Q2 with Henley at Hillside 3Feb 16, 2017 10:59 pm Sure thing... Land Like ⋅ Add a comment ⋅ Pin to Ideaboard ⋅ Color sections: Flooring and kitchen benchtop, cubboards and splashback Like ⋅ Add a comment ⋅ Pin to Ideaboard ⋅ Like ⋅ Add a comment ⋅ Pin to Ideaboard ⋅ Roof, bricks, render,gutter and garage Like ⋅ Add a comment ⋅ Pin to Ideaboard ⋅ bathroom tiles and carpet Like ⋅ Add a comment ⋅ Pin to Ideaboard ⋅ Construction progress for the past 4 weeks: Stage 1 - Base - complete Stage 2 - Frame - complete Like ⋅ Add a comment ⋅ Pin to Ideaboard ⋅ Stage 3 - lockup - In progress (ETA 24-Feb-2017) Re: Building Marina Q2 with Henley at Hillside 6Feb 17, 2017 11:47 am Yes, really exciting. Not sure if this the pace at which Henley operates. I'm expecting that the house will be done by the end of April. Fingers Crossed. Visiting the site today. Will post more pictures tonight... Re: Building Marina Q2 with Henley at Hillside 8Mar 23, 2017 10:09 pm Well, I'm overwhelmed with the progress. The construction actually started on 1st Feb 2017. Now the supervisor says that it might take end of April or first week of May 2017 to finish construction. Less than 3.5 months is pretty damn good in my opinion. Update: Fix stage completed on 20-Feb-2017. Painting work to commence next week. Uploading pictures soon... Re: Building Marina Q2 with Henley at Hillside 9Mar 23, 2017 10:10 pm Looks great Param! Didn't realise Henley built so fast! We bought in stage 3, they had only started digging a week ago... Any idea how long the LOT takes to get titled once they start digging? Thanks in advance Re: Building Marina Q2 with Henley at Hillside 10Mar 23, 2017 10:20 pm Thanks un4giv. I bought a ready-to-title land in Stage 2 (Stonybrook Estate, Hillside). Title was in October followed by Settlement in November. I can see that Stage 3 digging started this week and the Developer says the title will be ready by September 2017. That means 6 months. May not be same with every developer by the way. Re: Building Marina Q2 with Henley at Hillside 11Mar 23, 2017 10:23 pm Wow September.. Michael told me mid JUNE, that clearly wasn't correct lol But thanks for the information Param, at least I got a real estimate of when it's going to get titled =_= If anyone comes to this thread and is curious if they bought in later stages, we signed in August last year. Re: Building Marina Q2 with Henley at Hillside 12Mar 24, 2017 5:33 am Wow Param that is awesome! Such good news. I've had a few houses in my area go up in 3 months. Seems to be getting quicker! Yes I can see how your overwhelmed, my house has taken 6 weeks and I'm at lock-up already (with Henley). Would love to see photos when you have a chance Re: Building Marina Q2 with Henley at Hillside 13Mar 27, 2017 11:00 am Hi Param... Hope u doing great... good to see your house getting built so quickly....would u mind sharing your site supervisor's name..? I will see if I can get the same supervisor... Thanks Re: Building Marina Q2 with Henley at Hillside 14Mar 27, 2017 12:39 pm Thank you Mr.Singh, My Site Supervisor is Jason Iglesias. I learned from him that he looks after constructions in the North West suburbs (Hillside, Taylor's Lake, Caroline Springs etc...). Good luck with your build. Re: Building Marina Q2 with Henley at Hillside 15Mar 27, 2017 2:56 pm Here you go... Frame Stage Pictures: Like ⋅ Add a comment ⋅ Pin to Ideaboard ⋅ Like ⋅ Add a comment ⋅ Pin to Ideaboard ⋅ Like ⋅ Add a comment ⋅ Pin to Ideaboard ⋅ Like ⋅ Add a comment ⋅ Pin to Ideaboard ⋅ Like ⋅ Add a comment ⋅ Pin to Ideaboard ⋅ Like ⋅ Add a comment ⋅ Pin to Ideaboard ⋅ Like ⋅ Add a comment ⋅ Pin to Ideaboard ⋅ Like ⋅ Add a comment ⋅ Pin to Ideaboard ⋅ [b]Pre-Plaster Stage Pictures:[/b] [b] Like ⋅ Add a comment ⋅ Pin to Ideaboard ⋅ Like ⋅ Add a comment ⋅ Pin to Ideaboard ⋅ Like ⋅ Add a comment ⋅ Pin to Ideaboard ⋅ Like ⋅ Add a comment ⋅ Pin to Ideaboard ⋅ Like ⋅ Add a comment ⋅ Pin to Ideaboard ⋅ [/b] [b][/b] [b] Like ⋅ Add a comment ⋅ Pin to Ideaboard ⋅ [/b] [b]Pre-Paint Stage: [/b] [b] Like ⋅ Add a comment ⋅ Pin to Ideaboard ⋅ [/b] Like ⋅ Add a comment ⋅ Pin to Ideaboard ⋅ Re: Building Marina Q2 with Henley at Hillside 16Apr 26, 2017 5:39 pm Latest update: Construction is almost finished. Remaining items: - En-suite/Bathroom features and fixtures (bathtub/showers screen/taps etc..) - Timber laminates & Carpet New Home Presentation is scheduled on 9-May-2017 Re: Building Marina Q2 with Henley at Hillside 17Apr 26, 2017 5:47 pm Param2016 Latest update: Construction is almost finished. Remaining items: - En-suite/Bathroom features and fixtures (bathtub/showers screen/taps etc..) - Timber laminates & Carpet New Home Presentation is scheduled on 9-May-2017 Looks great you must be so excited Re: Building Marina Q2 with Henley at Hillside 18Apr 26, 2017 6:14 pm Very exciting. Last week we visited the construction site and here are the latest pictures. Main Door: Like ⋅ Add a comment ⋅ Pin to Ideaboard ⋅ Walk In Linen: Like ⋅ Add a comment ⋅ Pin to Ideaboard ⋅ Fridge Space and Plumbing for Water/Ice Dispenser: Like ⋅ Add a comment ⋅ Pin to Ideaboard ⋅ Butler's Pantry: Like ⋅ Add a comment ⋅ Pin to Ideaboard ⋅ Kitchen Bench top: Like ⋅ Add a comment ⋅ Pin to Ideaboard ⋅ Grand Island Bench top: Like ⋅ Add a comment ⋅ Pin to Ideaboard ⋅ Like ⋅ Add a comment ⋅ Pin to Ideaboard ⋅ Laundry: Like ⋅ Add a comment ⋅ Pin to Ideaboard ⋅ En-Suite Walk-In Robe: Like ⋅ Add a comment ⋅ Pin to Ideaboard ⋅ Laundry: Like ⋅ Add a comment ⋅ Pin to Ideaboard ⋅ Re: Building Marina Q2 with Henley at Hillside 20May 12, 2017 11:19 am Param2016 Construction completed on 1-May-2017 New Home Presentation completed on 9-May-2017 Home Occupancy Certificate due Next Week Settlement ETA Next Week Congrats! That's awesome news!! Can I ask you, when did you receive your final invoice? Was it once the house was completed or at the NHP? Hi, If you give a set of criteria as to what means 'good' to you, it'll give others prompts to respond. We considered Henley early on but there were two factors that… 1 10531 go upvc window frames ensure insulation under colorbond. not just sarking, lighter color roof also not sure if you have seen this viewtopic.php?t=5823 last couple of pages… 4 110592 |