We completed our pre-start on March 1st and just waiting for our unconditional finance from the bank and the land to title. Will post up some of our colour options and our floorplan

Slab Down 23/08
Bricks Completed 09/10
First Building Inspection 09/10
Roof Timber Started 18/10
Roof Timber Finished 20/10
Fascia Installed 20/10
Roof Tiles Started 02/11
Roof Tiles Finished 03/11
Render Float Complete 08/11
Ceilings and Cornices up 15/11
Windows and Most Doors in 23/11
Wardrobe Shelf Rail and Pantry in 23/11
Cabinets in 29/11